WK-2026-W21 · auto-generated · 50 voice notes → 1 page
Weekly Rollup — Ewing Creek - Brick Church Equalization Facility
Mon May 18 – Fri May 22, 2026 · Day 18 – Day 22 of 240 · 50 source recordings
Executive summary
- On schedule overall — critical path advanced 4 of 5 days; Monday's half weather day fully recovered.
- Equalization tank E-7 wall poured Tuesday (28 CY Irving), slab B-3 poured Wednesday (32 CY) — both stripped clean, zero rework.
- RFI-014 (anchor bolts, 4 days open at start of week) CLOSED Wed — submittal R1 sent Fri to civil engineer.
- PCO-007 pricing sent to Metro Water Fri AM ($87,400 + tax). Owner response expected Tuesday.
- Safety: 0 recordables, 2 documented near-misses (Mon rebar swing, Thu rebar slip), 5 toolbox talks delivered, 100% PPE compliance.
- Manpower trend: avg 22.6/day, peak 26 Wed, low 19 Mon (rain). Volunteer Rebar short Mon (#5 bars), recovered by Tue.
Progress vs. schedule
Planned
11.2%
Actual
11.4%
Variance
+0.2%
Critical path: equalization tank wall complex → slab → upper mat. Advanced 4 of 5 days. Float restored to 4 days end of week.
Milestones hit
- Equalization tank E-7 wall pour (Tue)
- Equalization tank G-J upper mat complete (Wed)
- Slab B-3 pour (Wed)
- Storm drainage MH-13 → MH-14 segment complete (Thu)
- Bioretention basin CMU through course 7 N elevation (Fri)
- B-1 anchor punch closed (Fri)
Manpower trends
Avg/day
22.6
Peak
26 (Wed)
Low
19 (Mon)
- Concrete (Premier)8.8/day (flat)
- Ironworkers (Steele)6/day (+0.5)
- Mechanical (Hutch)3.4/day (-0.2 (Mon parts run))
- Walker self-perform4/day (flat)
Consolidated open items
- RFI-014 — Anchor bolt qty/pattern for pump stationcivil engineer / Walker QC · 8 days open · closed
- PCO-007 — Added valve vault at sta 18+00 ($87,400 + tax)Nashville and Davidson County Metro Government · 22 days open · watch
- 11-2150-R1 — Pump station anchor pattern (resubmission)civil engineer · 0 days open · fresh
- EXPEDITE — Rinker gasket install — civil engineer-approved sub, install mid-next weekCumberland Utility Services · 5 days open · watch
- OWNER_DECISION — Weekly rollup cadence shift — owner now requires Mon 08:00 (not Fri)Walker PM · 1 day open · fresh
Safety
Recordables
0
Near-misses
2
PPE issues
1
Toolbox topics
- • Rigging and load swing safety (Mon)
- • Hot-work permits (Tue)
- • Fall protection (Wed)
- • Heat illness prevention (Thu)
- • SWPPP awareness (Fri)
Recurring issues
- Cumberland Utility Services flange gaskets — Mid-South Supply Friday ETA, repeat 3+ day issue, resolved via Rinker substitution (civil engineer-approved Thu)Observed 5 days · Standing alternate-supplier matrix for long-lead MEP fittings
- Volunteer Rebar blower-pad column ties — 5+ day backlog before delivery WednesdayObserved 5 days · Add column ties to weekly material call-off review with Volunteer Rebar PM
- Skytrak 10054 idle 4 days before return Wed — rental cost burnObserved 4 days · Walker Dispatch flag rule: equipment idle 2+ days surfaces in PM's Monday view
Materials
Received this week
- • 28 CY 4500-psi concrete Tue (IMI Concrete BOL 77192)
- • 32 CY 4500-psi concrete Wed (IMI Concrete BOL 77241)
- • 18 tons #5/#6 rebar Tue (Volunteer Rebar PO)
- • Bond beam grout Thu (BSi)
- • Volunteer Rebar column ties Wed (5+ day backlog cleared)
- • Rinker gaskets Fri (civil engineer-approved alternate)
Arriving next week
- • Pump station mat rebar (Volunteer Rebar PO)
- • Pump station components (June delivery, on schedule)
- • CMU course 8/9 (Builders Supply, Mon AM)
Next week look-ahead
- Mon May 25
- • Weekly rollup to owner 08:00
- • Pump station mat placement (Steele)
- • MH-13 → MH-14 pressure test (Hutch + QC)
- • Bioretention basin CMU course 8 N+E (Premier)
Risks: Pressure test fail would slip storm drainage critical path 2 days - Tue May 26
- • Owner monthly progress meeting (afternoon)
- • PCO-007 owner response expected
- • MH-14 → MH-15 pipe set begins
Risks: PCO denial would force scope rework - Wed May 27
- • Blower pad welding starts (hot-work permits ready)
- • Rinker gasket install (blower header)
- • Pump station mat continued
Risks: Hot work in CMU work zone — Karen pre-brief Tue afternoon - Thu May 28
- • Bioretention basin CMU course 9
- • Pump station mat completion target
- Fri May 29
- • Week wrap, weekly rollup draft
Photos
62 photos captured this week
Key milestones documented
- • Equalization tank E-7 wall pour (Tue, before/during/after)
- • Rebar inspection pass (L. Pham, Metro Water, Tue 07:45)
- • Slab B-3 pour (Wed)
- • Bioretention basin CMU course 6 placement (Thu)
- • Owner walk site progress (Thu 09:00)
- • SWPPP fence cleanup (Fri AM, TDEC file)
Cost signal
- • PCO-007 pending owner response: +$87,400 contract value if approved
- • Skytrak 10054 idle cost: ~$320 over 4 days before return (flagged for future material-flow improvement)
- • 1 truck concrete rejected Tue (slump-wet) — no charge, vendor absorbed
- • Rinker gasket sub: no cost impact vs original spec
- • Labor hours actual vs planned: +1% (within tolerance)
Source recordings
- John HutchisonSite Superintendent · SuperintendentEwing Creek - Brick Church Equalization FacilityMon May 18
- Marcus TranProject Engineer · Project EngineerEwing Creek - Brick Church Equalization FacilityMon May 18
- Sara PatelProject Manager · Project ManagerEwing Creek - Brick Church Equalization FacilityMon May 18
- Donny SteeleIronworker Foreman · ForemanEwing Creek - Brick Church Equalization FacilityMon May 18
- Ricky DiazConcrete Foreman · ForemanEwing Creek - Brick Church Equalization FacilityMon May 18
- Andre HutchMechanical Foreman · ForemanEwing Creek - Brick Church Equalization FacilityMon May 18
- Tom BriggsHeavy Equipment Operator · Equipment OperatorEwing Creek - Brick Church Equalization FacilityMon May 18
- Karen BoydSafety Officer · Safety OfficerEwing Creek - Brick Church Equalization FacilityMon May 18
- Luis MendezQC Officer · QC OfficerEwing Creek - Brick Church Equalization FacilityMon May 18
- Wes CarverOwner's Representative · Owner's RepEwing Creek - Brick Church Equalization FacilityMon May 18
- John HutchisonSite Superintendent · SuperintendentEwing Creek - Brick Church Equalization FacilityTue May 19
- Marcus TranProject Engineer · Project EngineerEwing Creek - Brick Church Equalization FacilityTue May 19
- Sara PatelProject Manager · Project ManagerEwing Creek - Brick Church Equalization FacilityTue May 19
- Donny SteeleIronworker Foreman · ForemanEwing Creek - Brick Church Equalization FacilityTue May 19
- Ricky DiazConcrete Foreman · ForemanEwing Creek - Brick Church Equalization FacilityTue May 19
- Andre HutchMechanical Foreman · ForemanEwing Creek - Brick Church Equalization FacilityTue May 19
- Tom BriggsHeavy Equipment Operator · Equipment OperatorEwing Creek - Brick Church Equalization FacilityTue May 19
- Karen BoydSafety Officer · Safety OfficerEwing Creek - Brick Church Equalization FacilityTue May 19
- Luis MendezQC Officer · QC OfficerEwing Creek - Brick Church Equalization FacilityTue May 19
- Wes CarverOwner's Representative · Owner's RepEwing Creek - Brick Church Equalization FacilityTue May 19
- John HutchisonSite Superintendent · SuperintendentEwing Creek - Brick Church Equalization FacilityWed May 20
- Marcus TranProject Engineer · Project EngineerEwing Creek - Brick Church Equalization FacilityWed May 20
- Sara PatelProject Manager · Project ManagerEwing Creek - Brick Church Equalization FacilityWed May 20
- Donny SteeleIronworker Foreman · ForemanEwing Creek - Brick Church Equalization FacilityWed May 20
- Ricky DiazConcrete Foreman · ForemanEwing Creek - Brick Church Equalization FacilityWed May 20
- Andre HutchMechanical Foreman · ForemanEwing Creek - Brick Church Equalization FacilityWed May 20
- Tom BriggsHeavy Equipment Operator · Equipment OperatorEwing Creek - Brick Church Equalization FacilityWed May 20
- Karen BoydSafety Officer · Safety OfficerEwing Creek - Brick Church Equalization FacilityWed May 20
- Luis MendezQC Officer · QC OfficerEwing Creek - Brick Church Equalization FacilityWed May 20
- Wes CarverOwner's Representative · Owner's RepEwing Creek - Brick Church Equalization FacilityWed May 20
- John HutchisonSite Superintendent · SuperintendentEwing Creek - Brick Church Equalization FacilityThu May 21
- Marcus TranProject Engineer · Project EngineerEwing Creek - Brick Church Equalization FacilityThu May 21
- Sara PatelProject Manager · Project ManagerEwing Creek - Brick Church Equalization FacilityThu May 21
- Donny SteeleIronworker Foreman · ForemanEwing Creek - Brick Church Equalization FacilityThu May 21
- Ricky DiazConcrete Foreman · ForemanEwing Creek - Brick Church Equalization FacilityThu May 21
- Andre HutchMechanical Foreman · ForemanEwing Creek - Brick Church Equalization FacilityThu May 21
- Tom BriggsHeavy Equipment Operator · Equipment OperatorEwing Creek - Brick Church Equalization FacilityThu May 21
- Karen BoydSafety Officer · Safety OfficerEwing Creek - Brick Church Equalization FacilityThu May 21
- Luis MendezQC Officer · QC OfficerEwing Creek - Brick Church Equalization FacilityThu May 21
- Wes CarverOwner's Representative · Owner's RepEwing Creek - Brick Church Equalization FacilityThu May 21
- John HutchisonSite Superintendent · SuperintendentEwing Creek - Brick Church Equalization FacilityFri May 22
- Marcus TranProject Engineer · Project EngineerEwing Creek - Brick Church Equalization FacilityFri May 22
- Sara PatelProject Manager · Project ManagerEwing Creek - Brick Church Equalization FacilityFri May 22
- Donny SteeleIronworker Foreman · ForemanEwing Creek - Brick Church Equalization FacilityFri May 22
- Ricky DiazConcrete Foreman · ForemanEwing Creek - Brick Church Equalization FacilityFri May 22
- Andre HutchMechanical Foreman · ForemanEwing Creek - Brick Church Equalization FacilityFri May 22
- Tom BriggsHeavy Equipment Operator · Equipment OperatorEwing Creek - Brick Church Equalization FacilityFri May 22
- Karen BoydSafety Officer · Safety OfficerEwing Creek - Brick Church Equalization FacilityFri May 22
- Luis MendezQC Officer · QC OfficerEwing Creek - Brick Church Equalization FacilityFri May 22
- Wes CarverOwner's Representative · Owner's RepEwing Creek - Brick Church Equalization FacilityFri May 22
- Rachel WhittakerProject Manager · Project ManagerMansker Creek Bank StabilizationMon May 18
- Ethan KwonSite Superintendent · SuperintendentMansker Creek Bank StabilizationMon May 18
- Jorge BurkeCivil Foreman · ForemanMansker Creek Bank StabilizationMon May 18
- Rachel WhittakerProject Manager · Project ManagerMansker Creek Bank StabilizationTue May 19
- Ethan KwonSite Superintendent · SuperintendentMansker Creek Bank StabilizationTue May 19
- Jorge BurkeCivil Foreman · ForemanMansker Creek Bank StabilizationTue May 19
56 recordings across 2 projects.
Voice-of-the-field
“Tell Sara.”
“The boys are happy, week's gone well.”
“Column ties still ain't here for the blower pad. Need somebody to chase that.”
“Anchor bolt RFI is still sitting with the civil engineer — four days. That's unacceptable for a critical-path item.”
“Zero recordable incidents week-to-date.”