WK-2026-W21 · auto-generated · 50 voice notes → 1 page

Weekly Rollup — Ewing Creek - Brick Church Equalization Facility

Mon May 18 – Fri May 22, 2026 · Day 18 – Day 22 of 240 · 50 source recordings

Executive summary
  • On schedule overall — critical path advanced 4 of 5 days; Monday's half weather day fully recovered.
  • Equalization tank E-7 wall poured Tuesday (28 CY Irving), slab B-3 poured Wednesday (32 CY) — both stripped clean, zero rework.
  • RFI-014 (anchor bolts, 4 days open at start of week) CLOSED Wed — submittal R1 sent Fri to civil engineer.
  • PCO-007 pricing sent to Metro Water Fri AM ($87,400 + tax). Owner response expected Tuesday.
  • Safety: 0 recordables, 2 documented near-misses (Mon rebar swing, Thu rebar slip), 5 toolbox talks delivered, 100% PPE compliance.
  • Manpower trend: avg 22.6/day, peak 26 Wed, low 19 Mon (rain). Volunteer Rebar short Mon (#5 bars), recovered by Tue.

Progress vs. schedule

Planned
11.2%
Actual
11.4%
Variance
+0.2%

Critical path: equalization tank wall complex → slab → upper mat. Advanced 4 of 5 days. Float restored to 4 days end of week.

Milestones hit
  • Equalization tank E-7 wall pour (Tue)
  • Equalization tank G-J upper mat complete (Wed)
  • Slab B-3 pour (Wed)
  • Storm drainage MH-13 → MH-14 segment complete (Thu)
  • Bioretention basin CMU through course 7 N elevation (Fri)
  • B-1 anchor punch closed (Fri)

Manpower trends

Avg/day
22.6
Peak
26 (Wed)
Low
19 (Mon)
  • Concrete (Premier)8.8/day (flat)
  • Ironworkers (Steele)6/day (+0.5)
  • Mechanical (Hutch)3.4/day (-0.2 (Mon parts run))
  • Walker self-perform4/day (flat)

Consolidated open items

  • RFI-014 Anchor bolt qty/pattern for pump station
    civil engineer / Walker QC · 8 days open · closed
  • PCO-007 Added valve vault at sta 18+00 ($87,400 + tax)
    Nashville and Davidson County Metro Government · 22 days open · watch
  • 11-2150-R1 Pump station anchor pattern (resubmission)
    civil engineer · 0 days open · fresh
  • EXPEDITE Rinker gasket install — civil engineer-approved sub, install mid-next week
    Cumberland Utility Services · 5 days open · watch
  • OWNER_DECISION Weekly rollup cadence shift — owner now requires Mon 08:00 (not Fri)
    Walker PM · 1 day open · fresh

Safety

Recordables
0
Near-misses
2
PPE issues
1
Toolbox topics
  • Rigging and load swing safety (Mon)
  • Hot-work permits (Tue)
  • Fall protection (Wed)
  • Heat illness prevention (Thu)
  • SWPPP awareness (Fri)

Recurring issues

  • Cumberland Utility Services flange gaskets — Mid-South Supply Friday ETA, repeat 3+ day issue, resolved via Rinker substitution (civil engineer-approved Thu)
    Observed 5 days · Standing alternate-supplier matrix for long-lead MEP fittings
  • Volunteer Rebar blower-pad column ties — 5+ day backlog before delivery Wednesday
    Observed 5 days · Add column ties to weekly material call-off review with Volunteer Rebar PM
  • Skytrak 10054 idle 4 days before return Wed — rental cost burn
    Observed 4 days · Walker Dispatch flag rule: equipment idle 2+ days surfaces in PM's Monday view

Materials

Received this week
  • 28 CY 4500-psi concrete Tue (IMI Concrete BOL 77192)
  • 32 CY 4500-psi concrete Wed (IMI Concrete BOL 77241)
  • 18 tons #5/#6 rebar Tue (Volunteer Rebar PO)
  • Bond beam grout Thu (BSi)
  • Volunteer Rebar column ties Wed (5+ day backlog cleared)
  • Rinker gaskets Fri (civil engineer-approved alternate)
Arriving next week
  • Pump station mat rebar (Volunteer Rebar PO)
  • Pump station components (June delivery, on schedule)
  • CMU course 8/9 (Builders Supply, Mon AM)

Next week look-ahead

  • Mon May 25
    • Weekly rollup to owner 08:00
    • Pump station mat placement (Steele)
    • MH-13 → MH-14 pressure test (Hutch + QC)
    • Bioretention basin CMU course 8 N+E (Premier)
    Risks: Pressure test fail would slip storm drainage critical path 2 days
  • Tue May 26
    • Owner monthly progress meeting (afternoon)
    • PCO-007 owner response expected
    • MH-14 → MH-15 pipe set begins
    Risks: PCO denial would force scope rework
  • Wed May 27
    • Blower pad welding starts (hot-work permits ready)
    • Rinker gasket install (blower header)
    • Pump station mat continued
    Risks: Hot work in CMU work zone — Karen pre-brief Tue afternoon
  • Thu May 28
    • Bioretention basin CMU course 9
    • Pump station mat completion target
  • Fri May 29
    • Week wrap, weekly rollup draft

Photos

62 photos captured this week

Key milestones documented
  • Equalization tank E-7 wall pour (Tue, before/during/after)
  • Rebar inspection pass (L. Pham, Metro Water, Tue 07:45)
  • Slab B-3 pour (Wed)
  • Bioretention basin CMU course 6 placement (Thu)
  • Owner walk site progress (Thu 09:00)
  • SWPPP fence cleanup (Fri AM, TDEC file)

Cost signal

  • PCO-007 pending owner response: +$87,400 contract value if approved
  • Skytrak 10054 idle cost: ~$320 over 4 days before return (flagged for future material-flow improvement)
  • 1 truck concrete rejected Tue (slump-wet) — no charge, vendor absorbed
  • Rinker gasket sub: no cost impact vs original spec
  • Labor hours actual vs planned: +1% (within tolerance)

Source recordings

  • John Hutchison
    Site Superintendent · Superintendent
    Ewing Creek - Brick Church Equalization Facility
    Mon May 18
  • Marcus Tran
    Project Engineer · Project Engineer
    Ewing Creek - Brick Church Equalization Facility
    Mon May 18
  • Sara Patel
    Project Manager · Project Manager
    Ewing Creek - Brick Church Equalization Facility
    Mon May 18
  • Donny Steele
    Ironworker Foreman · Foreman
    Ewing Creek - Brick Church Equalization Facility
    Mon May 18
  • Ricky Diaz
    Concrete Foreman · Foreman
    Ewing Creek - Brick Church Equalization Facility
    Mon May 18
  • Andre Hutch
    Mechanical Foreman · Foreman
    Ewing Creek - Brick Church Equalization Facility
    Mon May 18
  • Tom Briggs
    Heavy Equipment Operator · Equipment Operator
    Ewing Creek - Brick Church Equalization Facility
    Mon May 18
  • Karen Boyd
    Safety Officer · Safety Officer
    Ewing Creek - Brick Church Equalization Facility
    Mon May 18
  • Luis Mendez
    QC Officer · QC Officer
    Ewing Creek - Brick Church Equalization Facility
    Mon May 18
  • Wes Carver
    Owner's Representative · Owner's Rep
    Ewing Creek - Brick Church Equalization Facility
    Mon May 18
  • John Hutchison
    Site Superintendent · Superintendent
    Ewing Creek - Brick Church Equalization Facility
    Tue May 19
  • Marcus Tran
    Project Engineer · Project Engineer
    Ewing Creek - Brick Church Equalization Facility
    Tue May 19
  • Sara Patel
    Project Manager · Project Manager
    Ewing Creek - Brick Church Equalization Facility
    Tue May 19
  • Donny Steele
    Ironworker Foreman · Foreman
    Ewing Creek - Brick Church Equalization Facility
    Tue May 19
  • Ricky Diaz
    Concrete Foreman · Foreman
    Ewing Creek - Brick Church Equalization Facility
    Tue May 19
  • Andre Hutch
    Mechanical Foreman · Foreman
    Ewing Creek - Brick Church Equalization Facility
    Tue May 19
  • Tom Briggs
    Heavy Equipment Operator · Equipment Operator
    Ewing Creek - Brick Church Equalization Facility
    Tue May 19
  • Karen Boyd
    Safety Officer · Safety Officer
    Ewing Creek - Brick Church Equalization Facility
    Tue May 19
  • Luis Mendez
    QC Officer · QC Officer
    Ewing Creek - Brick Church Equalization Facility
    Tue May 19
  • Wes Carver
    Owner's Representative · Owner's Rep
    Ewing Creek - Brick Church Equalization Facility
    Tue May 19
  • John Hutchison
    Site Superintendent · Superintendent
    Ewing Creek - Brick Church Equalization Facility
    Wed May 20
  • Marcus Tran
    Project Engineer · Project Engineer
    Ewing Creek - Brick Church Equalization Facility
    Wed May 20
  • Sara Patel
    Project Manager · Project Manager
    Ewing Creek - Brick Church Equalization Facility
    Wed May 20
  • Donny Steele
    Ironworker Foreman · Foreman
    Ewing Creek - Brick Church Equalization Facility
    Wed May 20
  • Ricky Diaz
    Concrete Foreman · Foreman
    Ewing Creek - Brick Church Equalization Facility
    Wed May 20
  • Andre Hutch
    Mechanical Foreman · Foreman
    Ewing Creek - Brick Church Equalization Facility
    Wed May 20
  • Tom Briggs
    Heavy Equipment Operator · Equipment Operator
    Ewing Creek - Brick Church Equalization Facility
    Wed May 20
  • Karen Boyd
    Safety Officer · Safety Officer
    Ewing Creek - Brick Church Equalization Facility
    Wed May 20
  • Luis Mendez
    QC Officer · QC Officer
    Ewing Creek - Brick Church Equalization Facility
    Wed May 20
  • Wes Carver
    Owner's Representative · Owner's Rep
    Ewing Creek - Brick Church Equalization Facility
    Wed May 20
  • John Hutchison
    Site Superintendent · Superintendent
    Ewing Creek - Brick Church Equalization Facility
    Thu May 21
  • Marcus Tran
    Project Engineer · Project Engineer
    Ewing Creek - Brick Church Equalization Facility
    Thu May 21
  • Sara Patel
    Project Manager · Project Manager
    Ewing Creek - Brick Church Equalization Facility
    Thu May 21
  • Donny Steele
    Ironworker Foreman · Foreman
    Ewing Creek - Brick Church Equalization Facility
    Thu May 21
  • Ricky Diaz
    Concrete Foreman · Foreman
    Ewing Creek - Brick Church Equalization Facility
    Thu May 21
  • Andre Hutch
    Mechanical Foreman · Foreman
    Ewing Creek - Brick Church Equalization Facility
    Thu May 21
  • Tom Briggs
    Heavy Equipment Operator · Equipment Operator
    Ewing Creek - Brick Church Equalization Facility
    Thu May 21
  • Karen Boyd
    Safety Officer · Safety Officer
    Ewing Creek - Brick Church Equalization Facility
    Thu May 21
  • Luis Mendez
    QC Officer · QC Officer
    Ewing Creek - Brick Church Equalization Facility
    Thu May 21
  • Wes Carver
    Owner's Representative · Owner's Rep
    Ewing Creek - Brick Church Equalization Facility
    Thu May 21
  • John Hutchison
    Site Superintendent · Superintendent
    Ewing Creek - Brick Church Equalization Facility
    Fri May 22
  • Marcus Tran
    Project Engineer · Project Engineer
    Ewing Creek - Brick Church Equalization Facility
    Fri May 22
  • Sara Patel
    Project Manager · Project Manager
    Ewing Creek - Brick Church Equalization Facility
    Fri May 22
  • Donny Steele
    Ironworker Foreman · Foreman
    Ewing Creek - Brick Church Equalization Facility
    Fri May 22
  • Ricky Diaz
    Concrete Foreman · Foreman
    Ewing Creek - Brick Church Equalization Facility
    Fri May 22
  • Andre Hutch
    Mechanical Foreman · Foreman
    Ewing Creek - Brick Church Equalization Facility
    Fri May 22
  • Tom Briggs
    Heavy Equipment Operator · Equipment Operator
    Ewing Creek - Brick Church Equalization Facility
    Fri May 22
  • Karen Boyd
    Safety Officer · Safety Officer
    Ewing Creek - Brick Church Equalization Facility
    Fri May 22
  • Luis Mendez
    QC Officer · QC Officer
    Ewing Creek - Brick Church Equalization Facility
    Fri May 22
  • Wes Carver
    Owner's Representative · Owner's Rep
    Ewing Creek - Brick Church Equalization Facility
    Fri May 22
  • Rachel Whittaker
    Project Manager · Project Manager
    Mansker Creek Bank Stabilization
    Mon May 18
  • Ethan Kwon
    Site Superintendent · Superintendent
    Mansker Creek Bank Stabilization
    Mon May 18
  • Jorge Burke
    Civil Foreman · Foreman
    Mansker Creek Bank Stabilization
    Mon May 18
  • Rachel Whittaker
    Project Manager · Project Manager
    Mansker Creek Bank Stabilization
    Tue May 19
  • Ethan Kwon
    Site Superintendent · Superintendent
    Mansker Creek Bank Stabilization
    Tue May 19
  • Jorge Burke
    Civil Foreman · Foreman
    Mansker Creek Bank Stabilization
    Tue May 19

56 recordings across 2 projects.

Voice-of-the-field

Tell Sara.

John Hutchison · Multiple — Mon, Wed, Fri

The boys are happy, week's gone well.

Ricky Diaz · Thu May 21

Column ties still ain't here for the blower pad. Need somebody to chase that.

Donny Steele · Mon May 18 (resolved Wed)

Anchor bolt RFI is still sitting with the civil engineer — four days. That's unacceptable for a critical-path item.

Wes Carver (Metro Water) · Mon May 18 (closed Wed)

Zero recordable incidents week-to-date.

Karen Boyd · Thu May 21 (held through Fri)