Ewing Creek - Brick Church Equalization Facility
Week 21 of 2026 · 10 people · 50 voice notes · read the weekly rollup →
- Wes Carver· Owner's Representative0:58
Owner's rep on-site walk 14:00–15:30 with PM. Two items flagged: PCO-007 pricing commitment by Friday close; RFI-014 escalation from owner side tomorrow. Equalization tank forms observed clean. SWPPP holding.
- Sara Patel· Project Manager0:54
Site visit with Metro Water rep — pour prep on track for Tuesday. PCO-007 pricing commitment to owner reaffirmed for Friday. RFI-014 escalation tomorrow if no civil engineer response.
- Karen Boyd· Safety Officer1:02
Zero recordables. One near-miss (rebar bundle swing) — retrained on spot. Toolbox talk: rigging safety, 21 attendees. PPE issue: Premier saw operator gloves at EOL.
- Donny Steele· Ironworker Foreman0:42
Volunteer Rebar crew (4) tied ~70% of equalization tank G-J mat. Short on #5 rebar. Blower pad column ties still missing.
- Tom Briggs· Heavy Equipment Operator0:46
Cat 336 ran 3 hrs at pump station before rain shutdown. Skytrak 10054 idle 4 days — flagged for rental return. West gate muddy — recommend east-gate routing tomorrow.
- Luis Mendez· QC Officer0:39
Equalization tank wall forms within tolerance (Spec 03 30 00 §3.07). One punch item: anchor bolt B-1 at blower pad out of plumb. Metro Water rebar inspection rescheduled to Tuesday.
- Ricky Diaz· Concrete Foreman1:08
Pour prep on equalization tank E-7 paused for rain; forms preserved under canopy. Premier shifted to bioretention basin CMU (course 4 done, course 5 started). Tomorrow: pour 28 CY at 08:00 pending rebar inspection.
- Andre Hutch· Mechanical Foreman0:51
Cumberland Utility set 84 LF of 48-in RCP between MH-12 and MH-13. Joint test scheduled Tuesday. Flange gaskets still pending from Mid-South Supply — needs PM push.
- John Hutchison· Site Superintendent1:27
Equalization tank wall pour postponed to Tuesday due to heavy AM rain. Work shifted to bioretention basin CMU and rebar mat. One near-miss reported; RFI-014 still pending with civil engineer.
- Marcus Tran· Project Engineer1:13
Half weather day, equalization tank wall pour postponed to Tuesday. Bioretention basin CMU progressing. RFI-014 day 4 with civil engineer; PCO-007 pricing due Friday.
- Wes Carver· Owner's Representative0:44
No site visit. Owner pleased with civil engineer response on RFI-014; expects close-out plan from PM Wed. Thursday 09:00 site walk confirmed.
- Karen Boyd· Safety Officer0:49
Zero incidents, zero near-misses. Toolbox talk: hot-work permits (22 attendees). PPE issue from yesterday cleared.
- Sara Patel· Project Manager0:47
Pour day went well. RFI-014 close-out path set. PCO-007 send to owner Friday AM. Mid-South Supply gaskets stuck on Friday ETA — exploring alternate.
- Donny Steele· Ironworker Foreman0:38
Volunteer Rebar finished equalization tank G-J bottom mat, started uppers (~1/3 done). 18 tons #5/#6 rebar received. Blower-pad column ties STILL missing.
- Tom Briggs· Heavy Equipment Operator0:41
Cat 336 at pump station mass ex (4.5 hrs). Skytrak going out Wednesday. East-gate routing for trucks working clean.
- Andre Hutch· Mechanical Foreman0:56
MH-12 → MH-13 joint test passed (Luis Mendez witnessed). Next segment MH-13 → MH-14 prepped (~110 LF). Alternate gasket source (Rinker) identified — needs sub.
- Luis Mendez· QC Officer0:52
Rebar inspection passed. Joint pressure test passed. RFI-014 civil engineer response reviewed — compliant with Spec 11-2150. Recommending close-out Wed.
- Ricky Diaz· Concrete Foreman1:11
Equalization tank E-7 wall pour completed cleanly — 28 CY Irving, 1 truck rejected (wet slump). No honeycomb visible. Tomorrow: slab B-3 pour, ~32 CY.
- John Hutchison· Site Superintendent1:32
Equalization tank E-7 wall poured (28 CY Irving) — rebar inspection passed first thing. Hutch joint test MH-12→13 passed. RFI-014 finally answered by civil engineer mid-afternoon. Flange gaskets still pending Mid-South Supply.
- Marcus Tran· Project Engineer1:19
Equalization tank wall pour completed (28 CY Irving). Rebar inspection passed with minor punch corrected pre-pour. RFI-014 finally answered by civil engineer at 15:20.
- Wes Carver· Owner's Representative0:38
No site visit. Owner pleased with RFI-014 close + PCO-007 progress. Thursday 09:00 walk confirmed — wants E-7 strip, slab B-3, punch list read.
- Sara Patel· Project Manager0:51
RFI-014 closed. PCO-007 pricing locked ($87,400 + tax), sends Fri AM to Metro Water. Gasket sub to civil engineer Thu. Owner walk Thu 09:00.
- Karen Boyd· Safety Officer0:47
Zero recordables, zero near-misses, all PPE compliant. Toolbox talk: fall protection (26 attendees). Volunteer Rebar tie-off discipline observed clean.
- Donny Steele· Ironworker Foreman0:35
Volunteer Rebar finished upper mat equalization tank. Column ties FINALLY arrived (6+ day issue closed). Pump station rebar prep starts Thursday.
- Tom Briggs· Heavy Equipment Operator0:38
Mass ex at pump station complete. Skytrak rental return at 11:00. Genie boom idle.
- Andre Hutch· Mechanical Foreman0:53
Hutch set 65 LF of 110 LF MH-13 → MH-14 segment (~60% complete). Rinker gasket data sheet sent to PM — sub form to civil engineer Thursday.
- Ricky Diaz· Concrete Foreman1:04
Stripped E-7 (clean, no honeycomb). Poured slab B-3 (32 CY, no rejects, slump on target all 3 trucks). Tomorrow: strip B-3 + bioretention basin CMU course 6 if grout ready.
- Luis Mendez· QC Officer0:56
E-7 wall strip clean (Spec 03 30 00 §3.07). Slab B-3 pour on spec. RFI-014 close-out verified. Punch B-1 anchor re-set Thursday, re-inspect Friday AM.
- John Hutchison· Site Superintendent1:21
Best day of the week. E-7 wall stripped clean. Slab B-3 poured (32 CY). Upper mat complete. RFI-014 CLOSED. Gasket alternate plan locked.
- Marcus Tran· Project Engineer1:16
Strongest day of the week. E-7 wall stripped clean. Slab B-3 poured (32 CY, no rejects). RFI-014 CLOSED — submittal R1 goes Friday.
- Wes Carver· Owner's Representative1:07
Site walk satisfactory. Two owner asks: SWPPP cleanup by Fri close, weekly rollup to owner by Mon 08:00 (NOT Fri). RFI-014 close-out approved.
- Sara Patel· Project Manager0:52
Owner walk positive. Two new asks: SWPPP cleanup by Fri, weekly rollup to owner by Mon 08:00 (NOT Fri). PCO-007 send Fri AM locked. Gasket sub APPROVED by civil engineer.
- Karen Boyd· Safety Officer1:04
One near-miss (laborer rebar slip, no recordable). Toolbox talk: heat illness (24 attendees, hydration stations confirmed). Zero recordables WTD.
- Donny Steele· Ironworker Foreman0:36
Volunteer Rebar on two fronts — pump station rebar layout (5 of 7) and B-1 anchor punch fix (2 of 7, completed 14:00).
- Tom Briggs· Heavy Equipment Operator0:35
Cat 336 graded pump station pad (6 hrs). Genie boom 2 hrs hoisting CMU blocks for Premier.
- Ricky Diaz· Concrete Foreman1:01
Bond beam grout placed AM (BSi). Bioretention basin CMU course 6 — N+E elevations, ~410 SF. Tomorrow: strip B-3 + course 7.
- Andre Hutch· Mechanical Foreman0:49
MH-13 → MH-14 segment complete (110 LF). Gasket sub APPROVED by civil engineer — Rinker ships Fri, install mid-next week. Pressure test Monday.
- Luis Mendez· QC Officer0:47
Owner walk satisfactory. Bioretention basin course 6 ITP signed pre-pour, joints within tolerance. B-1 anchor re-set; re-inspect Fri AM w/ civil engineer pattern overlay.
- John Hutchison· Site Superintendent1:29
Owner walk satisfactory. Bioretention basin CMU course 6 placed. Punch B-1 anchor corrected. MH-13 → MH-14 segment complete. One minor near-miss (laborer rebar slip).
- Marcus Tran· Project Engineer1:21
Owner walk satisfactory; SWPPP flag at south fence. Bioretention basin CMU course 6 placed. B-1 anchor punch corrected. MH-13→14 segment complete. PCO-007 + Submittal R1 both Friday AM.
- Wes Carver· Owner's Representative0:39
PCO-007 received ($87,400 + tax), owner response Tue. Submittal R1 received, civil engineer review next week. SWPPP cleanup confirmed via photo file.
- Karen Boyd· Safety Officer0:56
Week stats clean — 5 toolbox talks, 2 near-misses, 0 recordables, 0 medical, 0 OSHA visits, 100% PPE compliance. Hot-work permits ready for Wed welding.
- Sara Patel· Project Manager0:49
PCO-007 received by owner 11:00. Submittal R1 out. Rinker in. SWPPP done. Good week to close — debrief Monday before rollup goes to owner 08:00.
- Donny Steele· Ironworker Foreman0:32
Volunteer Rebar finished pump station bottom mat prep. B-1 anchor inspection passed. Monday: mat placement.
- Tom Briggs· Heavy Equipment Operator0:38
SWPPP south fence cleanup (90 min, skid steer + 2 laborers). Pump station final grade (Cat 336, 5 hrs). Genie boom support for Hutch.
- Luis Mendez· QC Officer0:54
B-1 anchor re-inspection PASSED — punch item closed. Slab B-3 strip clean. Course 7 joints in tolerance. Week: 2 Metro Water passes, 3 internal QC sign-offs, RFI-014 closed, B-1 punch closed.
- Ricky Diaz· Concrete Foreman0:58
Slab B-3 stripped clean. Bioretention basin CMU course 7 N elevation done (220 SF). Week clean, no rework, no incidents.
- Andre Hutch· Mechanical Foreman0:47
MH-14 → MH-15 prep complete (~95 LF planned). Rinker gaskets received, count verified. Pressure test Mon, blower header install mid-next week.
- John Hutchison· Site Superintendent1:25
Week wrap. SWPPP fence cleaned. B-1 anchor re-inspection passed. Slab B-3 stripped. PCO-007 sent. Rinker gaskets received. Weekly rollup to owner Mon 08:00.
- Marcus Tran· Project Engineer1:18
PCO-007 SENT ($87,400 + tax). Submittal R1 SENT. Rinker gaskets received. B-1 anchor re-inspection PASSED. SWPPP done. Zero incidents WTD.