Marcus Tran
Project Engineer · Wed May 20, 2026 — Day 20 · voice note 1:16
What Marcus said
Marcus, Wednesday May 20th, Day 20. Weather, 76 sunny. Headcount 26, week peak. Wall strip on E-7 clean, no honeycomb, Luis signed. Slab B-3 pour, 32 CY Irving BOL 77241, no rejects, slump 4.0 on all three trucks. RFI-014 closed today — I sent confirmation to the civil engineer at 14:30 and updated the master log. New submittal package 11-2150-R1 goes out Friday with the corrected pattern. PCO-007 — Sara walked through pricing this afternoon, no changes, sends Friday AM. Gasket substitution package — Rinker comparable, going to civil engineer tomorrow AM. Volunteer Rebar finished upper mat. Hutch set 65 LF of pipe MH-13 to MH-14. Mass ex at pump station complete. Zero incidents on the day. 16 photos.
DR-2026-05-20-tran
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
Strongest day of the week. E-7 wall stripped clean. Slab B-3 poured (32 CY, no rejects). RFI-014 CLOSED — submittal R1 goes Friday.
- Equalization tank E-7 wall — form strip clean
- Slab B-3 — 32 CY IMI Concrete BOL 77241
- Equalization tank — upper mat complete (Steele)
- MH-13 → MH-14 — 65 LF of 110 LF set
- Pump station — mass ex complete
- Walker self — 4 + Karen + Luis
- Cumberland Concrete — 9 (R. Diaz)
- Volunteer Rebar — 7 (D. Steele)
- Cumberland Utility Services — 4 (A. Hutch)
- Total: 26 — week peak
- Received: 32 CY concrete IMI Concrete BOL 77241, slump 4.0 all 3 trucks
- Zero incidents
- E-7 wall strip — no honeycomb, L. Mendez sign-off
- Critical path on plan, float restored to 4 days.
- RFI-014 — CLOSED 14:30. Submittal 33-4100-R1 goes Fri.
- PCO-007 — pricing locked, sends Fri AM
- Gasket sub package — Rinker alternate, to civil engineer Thu AM
- 09:00 owner walk W. Carver
- Submit gasket substitution to civil engineer
- Slab B-3 strip prep
- 16 photos uploaded, geotagged