Wednesday, May 20
10 voice notes from 10 people · Ewing Creek - Brick Church Equalization Facility
- Wes Carver: No site visit. Owner pleased with RFI-014 close + PCO-007 progress. Thursday 09:00 walk confirmed — wants E-7 strip, slab B-3, punch list read.
- Sara Patel: RFI-014 closed. PCO-007 pricing locked ($87,400 + tax), sends Fri AM to Metro Water. Gasket sub to civil engineer Thu. Owner walk Thu 09:00.
- Karen Boyd: Zero recordables, zero near-misses, all PPE compliant. Toolbox talk: fall protection (26 attendees). Volunteer Rebar tie-off discipline observed clean.
- Donny Steele: Volunteer Rebar finished upper mat equalization tank. Column ties FINALLY arrived (6+ day issue closed). Pump station rebar prep starts Thursday.
- Tom Briggs: Mass ex at pump station complete. Skytrak rental return at 11:00. Genie boom idle.
- Andre Hutch: Hutch set 65 LF of 110 LF MH-13 → MH-14 segment (~60% complete). Rinker gasket data sheet sent to PM — sub form to civil engineer Thursday.
- Ricky Diaz: Stripped E-7 (clean, no honeycomb). Poured slab B-3 (32 CY, no rejects, slump on target all 3 trucks). Tomorrow: strip B-3 + bioretention basin CMU course 6 if grout ready.
- Luis Mendez: E-7 wall strip clean (Spec 03 30 00 §3.07). Slab B-3 pour on spec. RFI-014 close-out verified. Punch B-1 anchor re-set Thursday, re-inspect Friday AM.
- John Hutchison: Best day of the week. E-7 wall stripped clean. Slab B-3 poured (32 CY). Upper mat complete. RFI-014 CLOSED. Gasket alternate plan locked.
- Marcus Tran: Strongest day of the week. E-7 wall stripped clean. Slab B-3 poured (32 CY, no rejects). RFI-014 CLOSED — submittal R1 goes Friday.
Daily reports
- Wes Carver· Owner's Representative0:38
No site visit. Owner pleased with RFI-014 close + PCO-007 progress. Thursday 09:00 walk confirmed — wants E-7 strip, slab B-3, punch list read.
Open report → - Sara Patel· Project Manager0:51
RFI-014 closed. PCO-007 pricing locked ($87,400 + tax), sends Fri AM to Metro Water. Gasket sub to civil engineer Thu. Owner walk Thu 09:00.
Open report → - Karen Boyd· Safety Officer0:47
Zero recordables, zero near-misses, all PPE compliant. Toolbox talk: fall protection (26 attendees). Volunteer Rebar tie-off discipline observed clean.
Open report → - Donny Steele· Ironworker Foreman0:35
Volunteer Rebar finished upper mat equalization tank. Column ties FINALLY arrived (6+ day issue closed). Pump station rebar prep starts Thursday.
Open report → - Tom Briggs· Heavy Equipment Operator0:38
Mass ex at pump station complete. Skytrak rental return at 11:00. Genie boom idle.
Open report → - Andre Hutch· Mechanical Foreman0:53
Hutch set 65 LF of 110 LF MH-13 → MH-14 segment (~60% complete). Rinker gasket data sheet sent to PM — sub form to civil engineer Thursday.
Open report → - Ricky Diaz· Concrete Foreman1:04
Stripped E-7 (clean, no honeycomb). Poured slab B-3 (32 CY, no rejects, slump on target all 3 trucks). Tomorrow: strip B-3 + bioretention basin CMU course 6 if grout ready.
Open report → - Luis Mendez· QC Officer0:56
E-7 wall strip clean (Spec 03 30 00 §3.07). Slab B-3 pour on spec. RFI-014 close-out verified. Punch B-1 anchor re-set Thursday, re-inspect Friday AM.
Open report → - John Hutchison· Site Superintendent1:21
Best day of the week. E-7 wall stripped clean. Slab B-3 poured (32 CY). Upper mat complete. RFI-014 CLOSED. Gasket alternate plan locked.
Open report → - Marcus Tran· Project Engineer1:16
Strongest day of the week. E-7 wall stripped clean. Slab B-3 poured (32 CY, no rejects). RFI-014 CLOSED — submittal R1 goes Friday.
Open report →