Donny Steele

Ironworker Foreman · Wed May 20, 2026 — Day 20 · voice note 0:35

Step 1 — the voice note

What Donny said

Donny. Wednesday. Seven guys. Finished the upper mat equalization tank, all of it. Column ties came in late afternoon, finally. Tomorrow we start pump station rebar prep, five guys back to that, the other two on punch fixes. No injuries.

Step 2 — the generated daily report

DR-2026-05-20-steele

Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.

TL;DR

Volunteer Rebar finished upper mat equalization tank. Column ties FINALLY arrived (6+ day issue closed). Pump station rebar prep starts Thursday.

Work completed
  • Equalization tank upper mat — complete (Volunteer Rebar crew of 7)
Manpower
  • Volunteer Rebar — 7 + D. Steele
Materials
  • Received: column ties for blower pad (6+ day backlog closed)
Safety
  • No incidents
Tomorrow's plan
  • 5 of 7 to pump station rebar prep
  • 2 of 7 to punch fixes (B-1 anchor)

Not mentioned today: weather, equipment, inspections.