Ricky Diaz
Concrete Foreman · Wed May 20, 2026 — Day 20 · voice note 1:04
What Ricky said
Ricky, miércoles el 20. Nine guys. Stripped E-7 first thing, looked beautiful, no honeycomb, Luis signed off. Then Irving rolled in at 8:30 with 32 yards for slab B-3, three trucks, all on slump, no rejects. Poured by 11. Finishing crew on it through 14:30. Tomorrow we strip B-3 forms, start bioretention basin CMU course 6 if we can get the bond beam grout in time. Saw operator gloves working out. No accidents. Tell Sara my guys are happy with the gloves.
DR-2026-05-20-diaz
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
Stripped E-7 (clean, no honeycomb). Poured slab B-3 (32 CY, no rejects, slump on target all 3 trucks). Tomorrow: strip B-3 + bioretention basin CMU course 6 if grout ready.
- Equalization tank E-7 wall — form strip (clean)
- Slab B-3 — 32 CY IMI Concrete, 3 trucks all on spec, finishing through 14:30
- Cumberland Concrete — 9 + R. Diaz
- Received: 32 CY concrete IMI Concrete BOL 77241
- PPE: saw operator gloves performing well
- Zero incidents
- E-7 strip QC sign-off (L. Mendez)
- Strip slab B-3 forms
- Bioretention basin CMU course 6 (if bond beam grout ready)
Not mentioned today: weather, equipment.