Tom Briggs
Heavy Equipment Operator · Wed May 20, 2026 — Day 20 · voice note 0:38
Step 1 — the voice note
What Tom said
Tom, Wednesday. Finished mass ex at pump station, six hours on the Cat 336 today. Set the laydown for next week's rebar. Skytrak got picked up by United at 11. Genie boom not used. No incidents.
Step 2 — the generated daily report
DR-2026-05-20-briggs
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
TL;DR
Mass ex at pump station complete. Skytrak rental return at 11:00. Genie boom idle.
Work completed
- Pump station mass excavation — complete
- Pump station laydown — set for rebar staging
Equipment
- Cat 336 excavator (United UR-7732, rental) — 6 hrs run, finished mass ex pump station
- Skytrak 10054 — RETURNED to United 11:00 (rental cost stopped)
- Genie S-65 boom lift (owned) — not used
Safety
- No incidents
Tomorrow's plan
- Finish grading pump station, support bioretention basin bond-beam pour
Not mentioned today: manpower, materials, inspections, weather.