John Hutchison
Site Superintendent · Wed May 20, 2026 — Day 20 · voice note 1:21
What John said
Wednesday, the 20th, Day 20. Good day. Stripped E-7 forms first thing — clean, no honeycomb, Luis signed off. Premier poured slab B-3, 32 yards Irving, 8:30 delivery on time. Volunteer Rebar had seven guys, finished the upper mat equalization tank. Hutch laid pipe MH-13 to MH-14, about 65 feet of the 110, joints to test Friday. Tom finished mass ex at pump station, set the laydown for next week's rebar. RFI-014 closed — Marcus confirmed with the civil engineer, new submittal goes Friday. Gasket update — Sara talked to Andre, we're switching to Rinker, sub approval form goes to the civil engineer tomorrow. No safety incidents. 26 on site total, peak of the week. Tomorrow Wes is walking at 9, I'll do the loop with him. Tell Sara everything's on track for the PCO pricing.
DR-2026-05-20-hutchison
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
Best day of the week. E-7 wall stripped clean. Slab B-3 poured (32 CY). Upper mat complete. RFI-014 CLOSED. Gasket alternate plan locked.
- Equalization tank E-7 wall — forms stripped, clean (no honeycomb, QC sign-off)
- Slab B-3 — poured 32 CY IMI Concrete, 08:30 delivery
- Equalization tank upper mat — completed (Volunteer Rebar crew of 7)
- Storm drainage — 65 LF of 110 LF set MH-13 → MH-14
- Pump station — mass ex complete, laydown set
- Cumberland Concrete — 9 + R. Diaz
- Volunteer Rebar — 7 + D. Steele
- Cumberland Utility Services — 4 + A. Hutch
- Walker self — 4 + Karen + Luis
- Total: 26 (week peak)
- Received: 32 CY 4500-psi concrete (IMI Concrete, BOL 77241)
- Zero incidents
- E-7 wall form-strip — clean, no honeycomb, L. Mendez sign-off
- Critical path advanced, day 20 actuals matching plan. Float 4 days.
- RFI-014 — CLOSED. New submittal goes Friday.
- Gasket alternate — Rinker substitution form to civil engineer tomorrow
- PCO-007 — pricing on track for Fri AM send
- Thu 09:00 — W. Carver (Metro Water) site walk scheduled
- 09:00 owner walk w/ W. Carver
- Strip slab B-3 forms
- Hutch — finish MH-13 → MH-14 segment
- Volunteer Rebar — start rebar prep pump station
- 16 photos uploaded, geotagged