Thursday, May 21

10 voice notes from 10 people · Ewing Creek - Brick Church Equalization Facility

Day at a glance
  • Wes Carver: Site walk satisfactory. Two owner asks: SWPPP cleanup by Fri close, weekly rollup to owner by Mon 08:00 (NOT Fri). RFI-014 close-out approved.
  • Sara Patel: Owner walk positive. Two new asks: SWPPP cleanup by Fri, weekly rollup to owner by Mon 08:00 (NOT Fri). PCO-007 send Fri AM locked. Gasket sub APPROVED by civil engineer.
  • Karen Boyd: One near-miss (laborer rebar slip, no recordable). Toolbox talk: heat illness (24 attendees, hydration stations confirmed). Zero recordables WTD.
  • Donny Steele: Volunteer Rebar on two fronts — pump station rebar layout (5 of 7) and B-1 anchor punch fix (2 of 7, completed 14:00).
  • Tom Briggs: Cat 336 graded pump station pad (6 hrs). Genie boom 2 hrs hoisting CMU blocks for Premier.
  • Ricky Diaz: Bond beam grout placed AM (BSi). Bioretention basin CMU course 6 — N+E elevations, ~410 SF. Tomorrow: strip B-3 + course 7.
  • Andre Hutch: MH-13 → MH-14 segment complete (110 LF). Gasket sub APPROVED by civil engineer — Rinker ships Fri, install mid-next week. Pressure test Monday.
  • Luis Mendez: Owner walk satisfactory. Bioretention basin course 6 ITP signed pre-pour, joints within tolerance. B-1 anchor re-set; re-inspect Fri AM w/ civil engineer pattern overlay.
  • John Hutchison: Owner walk satisfactory. Bioretention basin CMU course 6 placed. Punch B-1 anchor corrected. MH-13 → MH-14 segment complete. One minor near-miss (laborer rebar slip).
  • Marcus Tran: Owner walk satisfactory; SWPPP flag at south fence. Bioretention basin CMU course 6 placed. B-1 anchor punch corrected. MH-13→14 segment complete. PCO-007 + Submittal R1 both Friday AM.

Daily reports