John Hutchison

Site Superintendent · Thu May 21, 2026 — Day 21 · voice note 1:29

Step 1 — the voice note

What John said

Thursday the 21st, Day 21. Wes walked at 9 with Sara and me, good walk, he was satisfied with the E-7 strip and the B-3 slab. Asked about the SWPPP at the south fence — there's some sediment buildup, I told him we'd run a clean by Friday. 24 on site. Premier on bioretention basin CMU course 6, north and east elevations, about 410 SF — bond beam grout came in at 9, we got it placed by 13. Volunteer Rebar had 7, five on pump station rebar prep, two on the B-1 anchor punch fix, set the corrected anchor mid-afternoon, Luis re-inspects Friday. Hutch finished MH-13 to MH-14 segment, all 110 feet. They'll start the prep for MH-14 to MH-15 Friday. Tom — graded pump station pad, ran 6 hours. One near-miss this afternoon — laborer slipped on the rebar mat moving between bays, didn't fall but caught himself on a chair, scuffed his knee, Karen wrote it up. PCO pricing — Sara confirmed Friday AM send. Anchor RFI is closed, submittal R1 goes tomorrow. Photos uploaded.

Step 2 — the generated daily report

DR-2026-05-21-hutchison

Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.

TL;DR

Owner walk satisfactory. Bioretention basin CMU course 6 placed. Punch B-1 anchor corrected. MH-13 → MH-14 segment complete. One minor near-miss (laborer rebar slip).

Work completed
  • Owner walk completed (W. Carver, 09:00) — satisfied with E-7 strip + slab B-3
  • Bioretention basin CMU course 6 — N and E elevations, ~410 SF (Premier)
  • Pump station — rebar prep started (Steele, 5 of 7)
  • Punch B-1 anchor bolt — corrected pattern set, awaits QC re-inspection Fri AM
  • Storm drainage MH-13 → MH-14 — segment complete (110 LF total)
  • Pump station pad — graded (T. Briggs, 6 hrs)
Manpower
  • Cumberland Concrete — 9 + R. Diaz
  • Volunteer Rebar — 7 + D. Steele
  • Cumberland Utility Services — 4 + A. Hutch
  • Walker self — 4 + Karen + Luis
  • Total: 24 on site
Materials
  • Received: bond beam grout (BSi, 09:00)
Safety
  • Near-miss PM — Walker laborer slipped on rebar mat between bays, caught self on chair, scuffed knee. K. Boyd documented. No recordable.
Inspections
  • Punch B-1 re-set awaits QC re-inspection Fri AM (L. Mendez)
Open items
  • SWPPP — sediment buildup south fence flagged by owner. Clean by Fri.
  • PCO-007 — Fri AM send confirmed
  • Submittal 33-4100-R1 — Fri send
Visitors
  • W. Carver (Nashville and Davidson County Metro Government) — site walk 09:00–10:30
Tomorrow's plan
  • SWPPP south fence clean
  • Re-inspect B-1 anchor (Mendez)
  • Send PCO-007 to Metro Water
  • Issue submittal 11-2150-R1
  • Hutch — prep MH-14 → MH-15
Photos
  • 18 photos uploaded, geotagged