Luis Mendez
QC Officer · Thu May 21, 2026 — Day 21 · voice note 0:47
What Luis said
Luis, Thursday. Owner walk with Wes 09:00, observed E-7 wall, slab B-3, bioretention basin course 6 — Wes was satisfied. ITP for bioretention basin course 6 reviewed with Premier pre-pour, signed. B-1 anchor punch was set this afternoon by Steele, I'll re-inspect Friday AM with the civil engineer's pattern overlay. Course 6 mortar joint observation — within tolerance. No deviations today.
DR-2026-05-21-mendez
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
Owner walk satisfactory. Bioretention basin course 6 ITP signed pre-pour, joints within tolerance. B-1 anchor re-set; re-inspect Fri AM w/ civil engineer pattern overlay.
- Bioretention basin CMU course 6 ITP — reviewed + signed pre-pour (Premier)
- Bioretention basin course 6 mortar joints — within tolerance
- Owner walk observation — E-7 wall, slab B-3, course 6, no deviations called
- B-1 anchor — re-inspect Fri AM w/ civil engineer pattern overlay
- W. Carver (owner walk)
- Re-inspect B-1 anchor 07:30
- Slab B-3 strip QC
- Pump station rebar layout review
Not mentioned today: manpower (QC float), safety, weather, materials.