Sara Patel
Project Manager · Thu May 21, 2026 — Day 21 · voice note 0:52
What Sara said
Sara, Thursday. Walk with Wes went well — he was complimentary about the E-7 wall. Two new items from him — SWPPP south fence cleanup by tomorrow, and he wants the weekly rollup in his inbox by Monday morning, not Friday. I told him Monday at 8. PCO-007 pricing reviewed with Marcus at 4, locked, sending tomorrow AM as planned. civil engineer responded on the gasket sub this afternoon — approved Rinker, so Hutch can proceed mid-next week as planned. Submittal R1 also sends tomorrow. Near-miss this afternoon, minor, Karen handling.
DR-2026-05-21-patel
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
Owner walk positive. Two new asks: SWPPP cleanup by Fri, weekly rollup to owner by Mon 08:00 (NOT Fri). PCO-007 send Fri AM locked. Gasket sub APPROVED by civil engineer.
- SWPPP south fence cleanup — by Fri
- Weekly rollup — owner deadline shifted to Mon 08:00 (was Fri)
- PCO-007 — Fri AM send locked
- Gasket sub — APPROVED by civil engineer, Hutch proceeds mid-next week
- 09:00–10:30 W. Carver site walk
- Send PCO-007 to Metro Water AM
- Send Submittal 33-4100-R1
- Coordinate SWPPP cleanup w/ J. Hutchison
Not mentioned today: work completed, manpower, materials, safety, weather.