Project Manager · Thu May 21, 2026 — Day 21 · voice note 0:52

Step 1 — the voice note

What Sara said

Sara, Thursday. Walk with Wes went well — he was complimentary about the E-7 wall. Two new items from him — SWPPP south fence cleanup by tomorrow, and he wants the weekly rollup in his inbox by Monday morning, not Friday. I told him Monday at 8. PCO-007 pricing reviewed with Marcus at 4, locked, sending tomorrow AM as planned. civil engineer responded on the gasket sub this afternoon — approved Rinker, so Hutch can proceed mid-next week as planned. Submittal R1 also sends tomorrow. Near-miss this afternoon, minor, Karen handling.

Step 2 — the generated daily report

DR-2026-05-21-patel

Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.

TL;DR

Owner walk positive. Two new asks: SWPPP cleanup by Fri, weekly rollup to owner by Mon 08:00 (NOT Fri). PCO-007 send Fri AM locked. Gasket sub APPROVED by civil engineer.

Open items
  • SWPPP south fence cleanup — by Fri
  • Weekly rollup — owner deadline shifted to Mon 08:00 (was Fri)
  • PCO-007 — Fri AM send locked
  • Gasket sub — APPROVED by civil engineer, Hutch proceeds mid-next week
Visitors
  • 09:00–10:30 W. Carver site walk
Tomorrow's plan
  • Send PCO-007 to Metro Water AM
  • Send Submittal 33-4100-R1
  • Coordinate SWPPP cleanup w/ J. Hutchison

Not mentioned today: work completed, manpower, materials, safety, weather.