Wes Carver

Owner's Representative · Thu May 21, 2026 — Day 21 · voice note 1:07

Step 1 — the voice note

What Wes said

Wes Carver, Metro Water. Thursday site walk with Sara and John, 09:00 to 10:30. Positive overall — the E-7 wall pour came out clean, no honeycomb, that's the standard I expect on this contract. Slab B-3 looked good. Bioretention basin course 6 placement happening during the walk, observed bond beam grout placement, fine. Two items I'm tagging — SWPPP south fence has sediment buildup, needs cleanup by Friday close — that's a TDEC exposure if we get rain. Two, I want the weekly rollup in my inbox by Monday 8 AM, not Friday — I want a chance to read it before our internal review Monday afternoon. PCO-007 — Sara confirmed Friday AM, I'll be looking for it. Anchor RFI close-out — good, glad that's behind us. Submittal R1 expected Friday. That's all for me.

Step 2 — the generated daily report

DR-2026-05-21-carver

Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.

TL;DR

Site walk satisfactory. Two owner asks: SWPPP cleanup by Fri close, weekly rollup to owner by Mon 08:00 (NOT Fri). RFI-014 close-out approved.

Inspections
  • Observation: E-7 wall pour clean, no honeycomb (within owner spec)
  • Observation: slab B-3 acceptable
  • Observation: bioretention basin course 6 bond beam grout placement, acceptable
Open items
  • SWPPP south fence cleanup — by Fri close (TDEC rain risk)
  • Weekly rollup to owner — by Mon 08:00 (shifted from Fri)
  • PCO-007 — Fri AM send confirmed
  • Submittal 33-4100-R1 — Fri send expected
Visitors
  • (self) site walk 09:00–10:30 w/ S. Patel + J. Hutchison
Tomorrow's plan
  • Watch for PCO-007 send
  • Watch for submittal R1

Not mentioned today: manpower, work completed, materials, safety.