Wes Carver
Owner's Representative · Thu May 21, 2026 — Day 21 · voice note 1:07
What Wes said
Wes Carver, Metro Water. Thursday site walk with Sara and John, 09:00 to 10:30. Positive overall — the E-7 wall pour came out clean, no honeycomb, that's the standard I expect on this contract. Slab B-3 looked good. Bioretention basin course 6 placement happening during the walk, observed bond beam grout placement, fine. Two items I'm tagging — SWPPP south fence has sediment buildup, needs cleanup by Friday close — that's a TDEC exposure if we get rain. Two, I want the weekly rollup in my inbox by Monday 8 AM, not Friday — I want a chance to read it before our internal review Monday afternoon. PCO-007 — Sara confirmed Friday AM, I'll be looking for it. Anchor RFI close-out — good, glad that's behind us. Submittal R1 expected Friday. That's all for me.
DR-2026-05-21-carver
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
Site walk satisfactory. Two owner asks: SWPPP cleanup by Fri close, weekly rollup to owner by Mon 08:00 (NOT Fri). RFI-014 close-out approved.
- Observation: E-7 wall pour clean, no honeycomb (within owner spec)
- Observation: slab B-3 acceptable
- Observation: bioretention basin course 6 bond beam grout placement, acceptable
- SWPPP south fence cleanup — by Fri close (TDEC rain risk)
- Weekly rollup to owner — by Mon 08:00 (shifted from Fri)
- PCO-007 — Fri AM send confirmed
- Submittal 33-4100-R1 — Fri send expected
- (self) site walk 09:00–10:30 w/ S. Patel + J. Hutchison
- Watch for PCO-007 send
- Watch for submittal R1
Not mentioned today: manpower, work completed, materials, safety.