Friday, May 22

10 voice notes from 10 people · Ewing Creek - Brick Church Equalization Facility

Day at a glance
  • Wes Carver: PCO-007 received ($87,400 + tax), owner response Tue. Submittal R1 received, civil engineer review next week. SWPPP cleanup confirmed via photo file.
  • Karen Boyd: Week stats clean — 5 toolbox talks, 2 near-misses, 0 recordables, 0 medical, 0 OSHA visits, 100% PPE compliance. Hot-work permits ready for Wed welding.
  • Sara Patel: PCO-007 received by owner 11:00. Submittal R1 out. Rinker in. SWPPP done. Good week to close — debrief Monday before rollup goes to owner 08:00.
  • Donny Steele: Volunteer Rebar finished pump station bottom mat prep. B-1 anchor inspection passed. Monday: mat placement.
  • Tom Briggs: SWPPP south fence cleanup (90 min, skid steer + 2 laborers). Pump station final grade (Cat 336, 5 hrs). Genie boom support for Hutch.
  • Luis Mendez: B-1 anchor re-inspection PASSED — punch item closed. Slab B-3 strip clean. Course 7 joints in tolerance. Week: 2 Metro Water passes, 3 internal QC sign-offs, RFI-014 closed, B-1 punch closed.
  • Ricky Diaz: Slab B-3 stripped clean. Bioretention basin CMU course 7 N elevation done (220 SF). Week clean, no rework, no incidents.
  • Andre Hutch: MH-14 → MH-15 prep complete (~95 LF planned). Rinker gaskets received, count verified. Pressure test Mon, blower header install mid-next week.
  • John Hutchison: Week wrap. SWPPP fence cleaned. B-1 anchor re-inspection passed. Slab B-3 stripped. PCO-007 sent. Rinker gaskets received. Weekly rollup to owner Mon 08:00.
  • Marcus Tran: PCO-007 SENT ($87,400 + tax). Submittal R1 SENT. Rinker gaskets received. B-1 anchor re-inspection PASSED. SWPPP done. Zero incidents WTD.

Daily reports