Andre Hutch

Mechanical Foreman · Fri May 22, 2026 — Day 22 · voice note 0:47

Step 1 — the voice note

What Andre said

Andre, Friday. Four guys. Prepped MH-14 to 15, laser set, ROW marked, about 95 LF planned. Rinker gaskets arrived at 1, count verified, all there. Pressure test on MH-13 to 14 is Monday. Blower header install mid-next week assuming everything tests clean. No injuries.

Step 2 — the generated daily report

DR-2026-05-22-hutch

Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.

TL;DR

MH-14 → MH-15 prep complete (~95 LF planned). Rinker gaskets received, count verified. Pressure test Mon, blower header install mid-next week.

Work completed
  • Storm drainage MH-14 → MH-15 prep — laser + ROW marked (~95 LF planned)
Manpower
  • Cumberland Utility Services — 4 + A. Hutch
Materials
  • Received: Rinker gaskets (count verified)
Safety
  • Zero incidents
Tomorrow's plan
  • Saturday off
  • Monday — MH-13→14 pressure test + start MH-14→15 pipe set

Not mentioned today: weather, equipment, inspections.