Marcus Tran
Project Engineer · Fri May 22, 2026 — Day 22 · voice note 1:18
What Marcus said
Marcus, Friday May 22nd, Day 22. Weather 78 sunny. Headcount 22. PCO-007 sent to Metro Water 09:15, 87,400 plus tax with line-item breakdown. Submittal 33-4100-R1 sent 10:00, civil engineer acknowledged receipt. Rinker gaskets arrived 13:00, Hutch verified count. B-1 anchor re-inspection at 07:30, Luis passed it, RFI-014 effectively closed. Slab B-3 strip clean. Bioretention basin course 7 N elevation, 220 SF. Clarifier 3 bottom mat prep done, mat placement Monday. SWPPP south fence done by 09:00. Weekly rollup draft is at Sara, we'll finalize Monday morning before 8 AM send. Zero safety today. WTD recordables zero. 14 photos. Good week to close out.
DR-2026-05-22-tran
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
PCO-007 SENT ($87,400 + tax). Submittal R1 SENT. Rinker gaskets received. B-1 anchor re-inspection PASSED. SWPPP done. Zero incidents WTD.
- PCO-007 sent to Metro Water 09:15
- Submittal 33-4100-R1 sent 10:00 (civil engineer acknowledged)
- B-1 anchor re-inspection passed 07:30 (L. Mendez)
- SWPPP south fence cleanup complete 09:00
- Slab B-3 strip clean
- Bioretention basin CMU course 7 N elevation 220 SF
- Pump station bottom mat prep complete
- Total: 22 on site, week avg 22.6
- Received: Rinker gaskets 13:00 (Hutch verified count)
- Sent: PCO-007 ($87,400 + tax) to Metro Water
- Sent: Submittal 33-4100-R1 (civil engineer acknowledged)
- Zero incidents today, zero recordables WTD
- B-1 anchor — PASSED, RFI-014 effectively closed
- Plan: 11.2% complete. Actual: 11.4%. Net of Monday weather, week closed +0.2%.
- Weekly rollup — finalize Mon AM, send to owner by 08:00
- Saturday — no work scheduled
- Monday — pump station mat placement, MH-13→14 pressure test, weekly rollup to owner 08:00
- 14 photos uploaded, geotagged