Wes Carver
Owner's Representative · Fri May 22, 2026 — Day 22 · voice note 0:39
Step 1 — the voice note
What Wes said
Wes Carver. Friday. PCO-007 received from Sara 09:15, 87,400 plus tax, I'll have a response Tuesday. Submittal R1 also received, civil engineer will review next week. SWPPP cleanup confirmed by Karen's photo file — good. Weekly rollup Monday 8 AM. Have a good weekend.
Step 2 — the generated daily report
DR-2026-05-22-carver
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
TL;DR
PCO-007 received ($87,400 + tax), owner response Tue. Submittal R1 received, civil engineer review next week. SWPPP cleanup confirmed via photo file.
Open items
- PCO-007 — owner response by Tue
- Submittal 33-4100-R1 — civil engineer review next week
- Weekly rollup — owner expects Mon 08:00
Tomorrow's plan
- Weekend off
Not mentioned today: manpower, work completed, materials, safety, weather, visitors.