Sara Patel
Project Manager · Fri May 22, 2026 — Day 22 · voice note 0:49
What Sara said
Sara, Friday. PCO-007 went to Wes at 9:15 with the line-item PDF, he confirmed receipt at 11. Submittal R1 also out. Rinker gaskets in. SWPPP done. Weekly rollup draft from Marcus is in good shape, I'll polish Saturday and we send Monday by 8. Good week — anchor RFI closed, owner walk satisfactory, no recordables, on-plan schedule. Monday I want to debrief the PCO submission with John and Marcus before the rollup goes out. That's it.
DR-2026-05-22-patel
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
PCO-007 received by owner 11:00. Submittal R1 out. Rinker in. SWPPP done. Good week to close — debrief Monday before rollup goes to owner 08:00.
- Weekly rollup — polish Sat, send to owner Mon 08:00
- Mon: debrief PCO submission w/ J. Hutchison + M. Tran
- Saturday — polish weekly rollup
- Mon AM — rollup send + PCO debrief
Not mentioned today: work completed, manpower, materials, safety, weather.