John Hutchison
Site Superintendent · Fri May 22, 2026 — Day 22 · voice note 1:25
What John said
Friday the 22nd, Day 22, end of week. SWPPP south fence cleaned first thing, Tom ran the skid with two laborers, took an hour and a half, done by 9 — TDEC-defensible per Karen. B-1 anchor re-inspection at 7:30 with Luis, passed. Slab B-3 forms stripped clean. Premier on bioretention basin course 7 — north only today, 220 SF, course 8 next week. Volunteer Rebar finished pump station bottom mat prep, ready for mat placement Monday. Hutch prepped MH-14 to 15. PCO-007 went to Metro Water this morning per Sara, $87,400 plus tax. Submittal R1 also sent. Rinker gaskets arrived this afternoon. Total 22 on site, week average came in at 22.6, good number. No safety incidents today. Tomorrow's Saturday, no crew unless we need recovery. Weekly rollup goes to Wes Monday 8 AM. Tell Sara I want to debrief the PCO submission Monday.
DR-2026-05-22-hutchison
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
Week wrap. SWPPP fence cleaned. B-1 anchor re-inspection passed. Slab B-3 stripped. PCO-007 sent. Rinker gaskets received. Weekly rollup to owner Mon 08:00.
- SWPPP south fence cleanup — complete 09:00 (TDEC-defensible)
- B-1 anchor re-inspection — PASSED (L. Mendez)
- Slab B-3 — forms stripped clean
- Bioretention basin CMU course 7 — N elevation, 220 SF
- Pump station — bottom mat prep complete (ready for placement Mon)
- Storm drainage — MH-14 → MH-15 prep complete
- Cumberland Concrete — 9 + R. Diaz
- Volunteer Rebar — 6 + D. Steele
- Cumberland Utility Services — 4 + A. Hutch
- Walker self — 3 + Karen + Luis
- Total: 22 on site (week avg 22.6)
- Received: Rinker gaskets (PM)
- Sent: PCO-007 pricing to Metro Water ($87,400 + tax)
- Sent: Submittal 33-4100-R1
- Zero incidents today, 1 minor near-miss this week, zero recordables WTD
- B-1 anchor re-inspect — PASSED (L. Mendez, 07:30)
- Week ended on plan. Float 4 days. Recovered Monday's half weather day.
- Weekly rollup to owner — Mon 08:00
- Saturday — no crew unless recovery needed
- Monday — pump station mat placement, bioretention basin course 8 prep, MH-13 → MH-14 pressure test
- 14 photos uploaded, geotagged