Donny Steele
Ironworker Foreman · Thu May 21, 2026 — Day 21 · voice note 0:36
Step 1 — the voice note
What Donny said
Donny. Thursday. Seven. Five on pump station rebar layout, two on the B-1 anchor punch fix, got it set by 14:00. Luis re-inspects Friday. Tomorrow same split, finish pump station bottom mat prep. No injuries.
Step 2 — the generated daily report
DR-2026-05-21-steele
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
TL;DR
Volunteer Rebar on two fronts — pump station rebar layout (5 of 7) and B-1 anchor punch fix (2 of 7, completed 14:00).
Work completed
- Pump station — rebar layout in progress (5 ironworkers)
- Punch B-1 anchor bolt — corrected pattern set 14:00 (2 ironworkers)
Manpower
- Volunteer Rebar — 7 + D. Steele
Safety
- No incidents
Open items
- B-1 anchor — QC re-inspect Fri AM
Tomorrow's plan
- Same crew split
- Finish pump station bottom mat prep
Not mentioned today: weather, equipment, inspections (today only re-inspect).