Ricky Diaz
Concrete Foreman · Thu May 21, 2026 — Day 21 · voice note 1:01
Step 1 — the voice note
What Ricky said
Ricky, jueves el 21, day 21. Nine guys. Bond beam grout came in at 9 from BSi, placed by 13. Then we started course 6 on bioretention basin, north and east elevations, about 410 square feet, mortared and pointed. Luis reviewed the course 6 ITP before we started, all good. Tomorrow we strip B-3 forms and start course 7 if the layout's right. The boys are happy, week's gone well. No accidents on my crew.
Step 2 — the generated daily report
DR-2026-05-21-diaz
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
TL;DR
Bond beam grout placed AM (BSi). Bioretention basin CMU course 6 — N+E elevations, ~410 SF. Tomorrow: strip B-3 + course 7.
Work completed
- Bioretention basin — bond beam grout placed 09:00–13:00 (BSi)
- Bioretention basin CMU course 6 — N+E elevations, ~410 SF mortared+pointed
Manpower
- Cumberland Concrete — 9 + R. Diaz
Materials
- Received: bond beam grout BSi 09:00
Safety
- Zero incidents
Inspections
- ITP course 6 reviewed pre-pour (L. Mendez)
Tomorrow's plan
- Strip slab B-3 forms
- Start bioretention basin CMU course 7
Not mentioned today: weather, equipment.