Andre Hutch
Mechanical Foreman · Thu May 21, 2026 — Day 21 · voice note 0:49
Step 1 — the voice note
What Andre said
Andre, Thursday. Four full crew. Finished the MH-13 to 14 segment, all 110 feet, joints bedded. Pressure test scheduled Monday with QC. Got word from Sara — civil engineer approved the Rinker gasket sub, so we're cleared. Rinker ships tomorrow, we install the blower header mid-next week. Tomorrow we prep MH-14 to MH-15. No injuries.
Step 2 — the generated daily report
DR-2026-05-21-hutch
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
TL;DR
MH-13 → MH-14 segment complete (110 LF). Gasket sub APPROVED by civil engineer — Rinker ships Fri, install mid-next week. Pressure test Monday.
Work completed
- Storm drainage MH-13 → MH-14 — complete (110 LF total)
Manpower
- Cumberland Utility Services — 4 + A. Hutch
Safety
- Zero incidents
Open items
- Rinker gasket — ships Fri, install mid-next week (civil engineer-approved)
Tomorrow's plan
- Prep MH-14 → MH-15 segment
Not mentioned today: materials (no deliveries), weather, equipment, inspections.