Andre Hutch

Mechanical Foreman · Thu May 21, 2026 — Day 21 · voice note 0:49

Step 1 — the voice note

What Andre said

Andre, Thursday. Four full crew. Finished the MH-13 to 14 segment, all 110 feet, joints bedded. Pressure test scheduled Monday with QC. Got word from Sara — civil engineer approved the Rinker gasket sub, so we're cleared. Rinker ships tomorrow, we install the blower header mid-next week. Tomorrow we prep MH-14 to MH-15. No injuries.

Step 2 — the generated daily report

DR-2026-05-21-hutch

Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.

TL;DR

MH-13 → MH-14 segment complete (110 LF). Gasket sub APPROVED by civil engineer — Rinker ships Fri, install mid-next week. Pressure test Monday.

Work completed
  • Storm drainage MH-13 → MH-14 — complete (110 LF total)
Manpower
  • Cumberland Utility Services — 4 + A. Hutch
Safety
  • Zero incidents
Open items
  • Rinker gasket — ships Fri, install mid-next week (civil engineer-approved)
Tomorrow's plan
  • Prep MH-14 → MH-15 segment

Not mentioned today: materials (no deliveries), weather, equipment, inspections.