Tuesday, May 19

10 voice notes from 10 people · Ewing Creek - Brick Church Equalization Facility

Day at a glance
  • Wes Carver: No site visit. Owner pleased with civil engineer response on RFI-014; expects close-out plan from PM Wed. Thursday 09:00 site walk confirmed.
  • Karen Boyd: Zero incidents, zero near-misses. Toolbox talk: hot-work permits (22 attendees). PPE issue from yesterday cleared.
  • Sara Patel: Pour day went well. RFI-014 close-out path set. PCO-007 send to owner Friday AM. Mid-South Supply gaskets stuck on Friday ETA — exploring alternate.
  • Donny Steele: Volunteer Rebar finished equalization tank G-J bottom mat, started uppers (~1/3 done). 18 tons #5/#6 rebar received. Blower-pad column ties STILL missing.
  • Tom Briggs: Cat 336 at pump station mass ex (4.5 hrs). Skytrak going out Wednesday. East-gate routing for trucks working clean.
  • Andre Hutch: MH-12 → MH-13 joint test passed (Luis Mendez witnessed). Next segment MH-13 → MH-14 prepped (~110 LF). Alternate gasket source (Rinker) identified — needs sub.
  • Luis Mendez: Rebar inspection passed. Joint pressure test passed. RFI-014 civil engineer response reviewed — compliant with Spec 11-2150. Recommending close-out Wed.
  • Ricky Diaz: Equalization tank E-7 wall pour completed cleanly — 28 CY Irving, 1 truck rejected (wet slump). No honeycomb visible. Tomorrow: slab B-3 pour, ~32 CY.
  • John Hutchison: Equalization tank E-7 wall poured (28 CY Irving) — rebar inspection passed first thing. Hutch joint test MH-12→13 passed. RFI-014 finally answered by civil engineer mid-afternoon. Flange gaskets still pending Mid-South Supply.
  • Marcus Tran: Equalization tank wall pour completed (28 CY Irving). Rebar inspection passed with minor punch corrected pre-pour. RFI-014 finally answered by civil engineer at 15:20.