Mechanical Foreman · Tue May 19, 2026 — Day 19 · voice note 0:56
What Andre said
Andre, Tuesday. Three guys back. Joint test on MH-12 to 13 ran from 9 to 11, full pressure cycle, all joints passed, Luis was there. Then we started prep for the next segment, MH-13 to MH-14, about 110 LF, set the laser, marked the alignment. Sara called me about the gasket alternate — I told her Rinker has a comparable spec and they could ship Wednesday, problem is it's a different SKU so we'd need a sub. I'll send her the data sheet tonight. No injuries.
DR-2026-05-19-hutch
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
MH-12 → MH-13 joint test passed (Luis Mendez witnessed). Next segment MH-13 → MH-14 prepped (~110 LF). Alternate gasket source (Rinker) identified — needs sub.
- Storm drainage — joint test MH-12 → MH-13 (09:00–11:00), full pressure cycle, all joints passed
- MH-13 → MH-14 segment prep — laser set, alignment marked (~110 LF planned)
- Cumberland Utility Services — 3 + A. Hutch
- Zero incidents
- Joint pressure test MH-12 → MH-13 — passed (witnessed L. Mendez)
- Gasket alternate — Rinker comparable spec, ships Wed, requires substitution approval. Data sheet to PM tonight.
- Begin pipe set MH-13 → MH-14 (110 LF)
Not mentioned today: equipment, weather, materials (no deliveries).