Andre Hutch

Mechanical Foreman · Tue May 19, 2026 — Day 19 · voice note 0:56

Step 1 — the voice note

What Andre said

Andre, Tuesday. Three guys back. Joint test on MH-12 to 13 ran from 9 to 11, full pressure cycle, all joints passed, Luis was there. Then we started prep for the next segment, MH-13 to MH-14, about 110 LF, set the laser, marked the alignment. Sara called me about the gasket alternate — I told her Rinker has a comparable spec and they could ship Wednesday, problem is it's a different SKU so we'd need a sub. I'll send her the data sheet tonight. No injuries.

Step 2 — the generated daily report

DR-2026-05-19-hutch

Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.

TL;DR

MH-12 → MH-13 joint test passed (Luis Mendez witnessed). Next segment MH-13 → MH-14 prepped (~110 LF). Alternate gasket source (Rinker) identified — needs sub.

Work completed
  • Storm drainage — joint test MH-12 → MH-13 (09:00–11:00), full pressure cycle, all joints passed
  • MH-13 → MH-14 segment prep — laser set, alignment marked (~110 LF planned)
Manpower
  • Cumberland Utility Services — 3 + A. Hutch
Safety
  • Zero incidents
Inspections
  • Joint pressure test MH-12 → MH-13 — passed (witnessed L. Mendez)
Open items
  • Gasket alternate — Rinker comparable spec, ships Wed, requires substitution approval. Data sheet to PM tonight.
Tomorrow's plan
  • Begin pipe set MH-13 → MH-14 (110 LF)

Not mentioned today: equipment, weather, materials (no deliveries).