Luis Mendez
QC Officer · Tue May 19, 2026 — Day 19 · voice note 0:52
What Luis said
Luis, Tuesday. Rebar inspection passed with Pham, 07:45, equalization tank E-7 — minor punch E-3 chairs added before the pour. Pour observation — first truck good, second wet, rejected, third good, slump per spec on the third. Joint pressure test MH-12 to 13 passed with Hutch, 09:00 to 11:00. RFI-014 — civil engineer responded at 15:20, I reviewed the corrected pattern tonight, it's compliant with Spec 11-2150. Recommending Marcus close the RFI Wednesday and re-issue the submittal. Punch item B-1 anchor bolt remains open pending the new pattern application.
DR-2026-05-19-mendez
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
Rebar inspection passed. Joint pressure test passed. RFI-014 civil engineer response reviewed — compliant with Spec 11-2150. Recommending close-out Wed.
- Metro Water rebar inspection — L. Pham 07:45, equalization tank E-7 — passed (E-3 chairs corrected pre-pour)
- Concrete pour QC — 1st truck good, 2nd wet (rejected), 3rd on spec (slump 4.25)
- Joint pressure test MH-12 → MH-13 — passed (witnessed)
- RFI-014 — civil engineer response 15:20, compliant w/ Spec 11-2150. Recommend close-out Wed + re-issue submittal.
- Punch B-1 anchor bolt — remains open pending new pattern application.
- Close RFI-014 with M. Tran
- Observe slab B-3 pour
- Re-inspect anchor bolt B-1 after re-set
Not mentioned today: manpower (QC float), safety, weather, materials.