Marcus Tran

Project Engineer · Tue May 19, 2026 — Day 19 · voice note 1:19

Step 1 — the voice note

What Marcus said

Marcus, Tuesday May 19th, daily for the Ewing Creek, Day 19. Weather, 72 sunny, no impact. Headcount 22. Major item: equalization tank E-7 wall pour completed today, 28 CY IMI Concrete, BOL 77192 on file. One truck rejected for slump — wet, sent back, no penalty. Rebar inspection passed with L. Pham, 07:45, minor punch at E-3 corrected before pour. RFI-014 the big update — civil engineer responded at 15:20 with the corrected anchor pattern, Luis is reviewing tonight, I'll close the loop with the civil engineer tomorrow if confirmation lands. PCO-007 pricing draft is done, Sara reviewing, sends to Metro Water Friday. Submittal 33-4100 still pending. Hutch joint test passed MH-12 to 13, full pressure cycle. Tomorrow we strip E-7, slab B-3 pour with reinforcement done, Hutch continues to MH-14. 14 photos uploaded.

Step 2 — the generated daily report

DR-2026-05-19-tran

Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.

TL;DR

Equalization tank wall pour completed (28 CY Irving). Rebar inspection passed with minor punch corrected pre-pour. RFI-014 finally answered by civil engineer at 15:20.

Work completed
  • Equalization tank E-7 wall — poured 28 CY (Irving BOL 77192, 1 truck rejected slump)
  • MH-12 → MH-13 joint test — passed
  • Slab B-3 reinforcement complete (ready for Wed pour)
Manpower
  • Walker self — 4
  • Cumberland Concrete — 9 (R. Diaz)
  • Volunteer Rebar — 6 (D. Steele)
  • Cumberland Utility Services — 3 (A. Hutch)
  • Total: 22 on site
Materials
  • Received: 28 CY 4500-psi concrete (IMI Concrete, BOL 77192)
  • Rejected: 1 truck slump-wet, sent back, no penalty
Inspections
  • Metro Water rebar inspection — L. Pham, 07:45 — passed (minor punch E-3 chairs corrected pre-pour)
Schedule impact
  • Critical path recovered. Float restored to 4 days.
Open items
  • RFI-014 — civil engineer responded 15:20 with corrected pattern. QC reviewing. Close-out tomorrow if confirmed.
  • PCO-007 — pricing draft complete, S. Patel reviewing, send to Metro Water Friday.
  • Submittal 33-4100 — still pending civil engineer.
Tomorrow's plan
  • Strip E-7 wall forms
  • Premier — pour slab B-3
  • Volunteer Rebar — upper mat equalization tank
  • Hutch — pipe set MH-13 → MH-14
Photos
  • 14 photos uploaded, geotagged