John Hutchison

Site Superintendent · Tue May 19, 2026 — Day 19 · voice note 1:32

Step 1 — the voice note

What John said

Tuesday, the 19th, Day 19. Big day. Weather held — 72 high, no precip, ground was workable by 8. Pham came at 7:45 like Luis said, passed the rebar mat, asked for extra chairs at E-3, Premier set them before the truck got there. IMI Concrete rolled in at 8:05 with 28 yards, first truck slumped on target, second one was wet, we sent it back, third one we got the spread. Premier had nine guys plus Ricky, poured E-7 wall by 11:30, finishing 12 to 14, looked clean. Volunteer Rebar finished the G-J mat, started the uppers, six guys today including Donny. Hutch had three back, ran the joint test on MH-12 to 13, all passed. Tom moved out to pump station with the 336, started mass ex prep, about four and a half hours run. Gaskets still aren't here for Hutch, Mid-South Supply's holding the line at Friday — Sara's chasing. Anchor bolt RFI — civil engineer finally responded mid-afternoon, gave us the corrected pattern, Luis is reviewing tonight. Tomorrow we strip the E-7 forms first thing, Premier on slab pour at B-3 reinforcement, Volunteer Rebar on uppers, Hutch on the next pipe segment to MH-14. Twelve photos. Tell Sara about the gaskets again.

Step 2 — the generated daily report

DR-2026-05-19-hutchison

Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.

TL;DR

Equalization tank E-7 wall poured (28 CY Irving) — rebar inspection passed first thing. Hutch joint test MH-12→13 passed. RFI-014 finally answered by civil engineer mid-afternoon. Flange gaskets still pending Mid-South Supply.

Work completed
  • Equalization tank E-7 — wall pour 28 CY (Irving), poured 08:05–11:30, finishing 12:00–14:00
  • Equalization tank G-J mat completed, uppers started (Steele)
  • Storm drainage — joint test MH-12 → MH-13 passed (Cumberland Utility + QC)
  • Pump station — mass ex prep started (Cat 336, T. Briggs, 4.5 hrs)
Manpower
  • Cumberland Concrete — 9 + R. Diaz
  • Volunteer Rebar — 6 + D. Steele
  • Cumberland Utility Services — 3 + A. Hutch
  • Walker self — 4
  • Total: 22 on site
Materials
  • Received — 28 CY 4500-psi concrete IMI Concrete BOL 77192 (1 truck rejected slump-wet)
  • Short — flange gaskets Cumberland Utility (Mid-South Supply ETA Fri) — repeat issue
Inspections
  • Metro Water rebar inspection — L. Pham, 07:45, equalization tank E-7 — passed (note: add chairs at E-3, corrected before pour)
Schedule impact
  • Critical path back on track. Recovered Monday's half-day.
Open items
  • RFI-014 — civil engineer responded mid-afternoon with corrected pattern, Luis Mendez reviewing.
  • Need PM push on Mid-South Supply flange gaskets
Tomorrow's plan
  • Strip E-7 forms first thing
  • Premier — slab B-3 reinforcement and pour
  • Volunteer Rebar — upper mat equalization tank
  • Hutch — pipe set MH-13 → MH-14
Photos
  • 12 photos uploaded, geotagged

Not mentioned today: equipment idle detail.