John Hutchison
Site Superintendent · Tue May 19, 2026 — Day 19 · voice note 1:32
What John said
Tuesday, the 19th, Day 19. Big day. Weather held — 72 high, no precip, ground was workable by 8. Pham came at 7:45 like Luis said, passed the rebar mat, asked for extra chairs at E-3, Premier set them before the truck got there. IMI Concrete rolled in at 8:05 with 28 yards, first truck slumped on target, second one was wet, we sent it back, third one we got the spread. Premier had nine guys plus Ricky, poured E-7 wall by 11:30, finishing 12 to 14, looked clean. Volunteer Rebar finished the G-J mat, started the uppers, six guys today including Donny. Hutch had three back, ran the joint test on MH-12 to 13, all passed. Tom moved out to pump station with the 336, started mass ex prep, about four and a half hours run. Gaskets still aren't here for Hutch, Mid-South Supply's holding the line at Friday — Sara's chasing. Anchor bolt RFI — civil engineer finally responded mid-afternoon, gave us the corrected pattern, Luis is reviewing tonight. Tomorrow we strip the E-7 forms first thing, Premier on slab pour at B-3 reinforcement, Volunteer Rebar on uppers, Hutch on the next pipe segment to MH-14. Twelve photos. Tell Sara about the gaskets again.
DR-2026-05-19-hutchison
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
Equalization tank E-7 wall poured (28 CY Irving) — rebar inspection passed first thing. Hutch joint test MH-12→13 passed. RFI-014 finally answered by civil engineer mid-afternoon. Flange gaskets still pending Mid-South Supply.
- Equalization tank E-7 — wall pour 28 CY (Irving), poured 08:05–11:30, finishing 12:00–14:00
- Equalization tank G-J mat completed, uppers started (Steele)
- Storm drainage — joint test MH-12 → MH-13 passed (Cumberland Utility + QC)
- Pump station — mass ex prep started (Cat 336, T. Briggs, 4.5 hrs)
- Cumberland Concrete — 9 + R. Diaz
- Volunteer Rebar — 6 + D. Steele
- Cumberland Utility Services — 3 + A. Hutch
- Walker self — 4
- Total: 22 on site
- Received — 28 CY 4500-psi concrete IMI Concrete BOL 77192 (1 truck rejected slump-wet)
- Short — flange gaskets Cumberland Utility (Mid-South Supply ETA Fri) — repeat issue
- Metro Water rebar inspection — L. Pham, 07:45, equalization tank E-7 — passed (note: add chairs at E-3, corrected before pour)
- Critical path back on track. Recovered Monday's half-day.
- RFI-014 — civil engineer responded mid-afternoon with corrected pattern, Luis Mendez reviewing.
- Need PM push on Mid-South Supply flange gaskets
- Strip E-7 forms first thing
- Premier — slab B-3 reinforcement and pour
- Volunteer Rebar — upper mat equalization tank
- Hutch — pipe set MH-13 → MH-14
- 12 photos uploaded, geotagged
Not mentioned today: equipment idle detail.