Ricky Diaz

Concrete Foreman · Tue May 19, 2026 — Day 19 · voice note 1:11

Step 1 — the voice note

What Ricky said

Ricky, martes el 19, day 19. Big day, we poured. Nine guys today. Pham came at 7:45, passed the rebar mat, asked for extra chairs at E-3, my guys had them set before Irving rolled in. First truck at 8:05, slump was perfect, four and a quarter. Second truck came in too wet, almost six, we sent it back, no charge. Third truck got us back on spec. Finished the wall pour at 11:30, finishing crew took it to 14:00. Looked clean, no honeycomb on the form strip preview. Tomorrow we strip E-7, pour slab B-3, about 32 yards, Irving confirmed 8:30 delivery. Volunteer Rebar finished his rebar this morning so we're not waiting on him. Saw operator gloves came in, thanks. No accidents.

Step 2 — the generated daily report

DR-2026-05-19-diaz

Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.

TL;DR

Equalization tank E-7 wall pour completed cleanly — 28 CY Irving, 1 truck rejected (wet slump). No honeycomb visible. Tomorrow: slab B-3 pour, ~32 CY.

Work completed
  • Equalization tank E-7 wall pour — 08:05–11:30 (28 CY IMI Concrete, BOL 77192)
  • Finishing — 12:00–14:00, no visible honeycomb on form-strip preview
Manpower
  • Cumberland Concrete — 9 + R. Diaz
Materials
  • Received: 28 CY 4500-psi concrete IMI Concrete BOL 77192
  • Rejected: 1 truck slump 5.75 (spec 3-5), sent back
  • PPE: saw operator gloves received
Safety
  • Zero incidents
Inspections
  • 07:45 rebar inspection passed (L. Pham Metro Water), E-3 chair add corrected pre-pour
Tomorrow's plan
  • Strip E-7 forms (after 16 hr cure)
  • Pour slab B-3, ~32 CY IMI Concrete 08:30

Not mentioned today: equipment, weather detail.