Tom Briggs

Heavy Equipment Operator · Tue May 19, 2026 — Day 19 · voice note 0:41

Step 1 — the voice note

What Tom said

Tom, Tuesday. Ran the Cat 336 at pump station, four and a half hours, started mass excavation. Genie boom four hours run, used it to set the canopy frames at equalization tank. Skytrak 10054 — John called rental, it's going out tomorrow. Trucks routed through east gate per yesterday, no issues. No incidents.

Step 2 — the generated daily report

DR-2026-05-19-briggs

Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.

TL;DR

Cat 336 at pump station mass ex (4.5 hrs). Skytrak going out Wednesday. East-gate routing for trucks working clean.

Work completed
  • Pump station — mass excavation started
  • Equalization tank — canopy frames set
Equipment
  • Cat 336 excavator (United UR-7732, rental) — 4.5 hrs run, mass ex pump station
  • Genie S-65 boom lift (owned) — 4 hrs run, canopy frames equalization tank
  • Skytrak 10054 — going out Wed (J. Hutchison called rental)
Safety
  • No incidents
Tomorrow's plan
  • Continue mass ex pump station
  • Skytrak rental return

Not mentioned today: manpower (operator-only), materials, inspections, weather.