Wes Carver

Owner's Representative · Tue May 19, 2026 — Day 19 · voice note 0:44

Step 1 — the voice note

What Wes said

Wes Carver. Tuesday quick note, no site visit today. Confirmed with Pham the rebar inspection passed. Pleased to hear the civil engineer finally responded on RFI-014 — Sara should circle back tomorrow with the closure plan. I'll plan to walk the site Thursday AM as scheduled, 09:00. Want to see the E-7 wall stripped and the slab B-3 work. PCO-007 pricing — Friday close, no slippage.

Step 2 — the generated daily report

DR-2026-05-19-carver

Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.

TL;DR

No site visit. Owner pleased with civil engineer response on RFI-014; expects close-out plan from PM Wed. Thursday 09:00 site walk confirmed.

Inspections
  • Confirmed rebar inspection passed (per L. Pham)
Open items
  • RFI-014 — expecting close-out plan from S. Patel Wed
  • PCO-007 — Fri close, no slippage
Visitors
  • (no on-site visit Tue)
Tomorrow's plan
  • Thu AM 09:00 site walk scheduled — review E-7 strip, slab B-3

Not mentioned today: manpower, work completed, materials, safety.