Monday, May 18
10 voice notes from 10 people · Ewing Creek - Brick Church Equalization Facility
- Wes Carver: Owner's rep on-site walk 14:00–15:30 with PM. Two items flagged: PCO-007 pricing commitment by Friday close; RFI-014 escalation from owner side tomorrow. Equalization tank forms observed clean. SWPPP holding.
- Sara Patel: Site visit with Metro Water rep — pour prep on track for Tuesday. PCO-007 pricing commitment to owner reaffirmed for Friday. RFI-014 escalation tomorrow if no civil engineer response.
- Karen Boyd: Zero recordables. One near-miss (rebar bundle swing) — retrained on spot. Toolbox talk: rigging safety, 21 attendees. PPE issue: Premier saw operator gloves at EOL.
- Donny Steele: Volunteer Rebar crew (4) tied ~70% of equalization tank G-J mat. Short on #5 rebar. Blower pad column ties still missing.
- Tom Briggs: Cat 336 ran 3 hrs at pump station before rain shutdown. Skytrak 10054 idle 4 days — flagged for rental return. West gate muddy — recommend east-gate routing tomorrow.
- Luis Mendez: Equalization tank wall forms within tolerance (Spec 03 30 00 §3.07). One punch item: anchor bolt B-1 at blower pad out of plumb. Metro Water rebar inspection rescheduled to Tuesday.
- Ricky Diaz: Pour prep on equalization tank E-7 paused for rain; forms preserved under canopy. Premier shifted to bioretention basin CMU (course 4 done, course 5 started). Tomorrow: pour 28 CY at 08:00 pending rebar inspection.
- Andre Hutch: Cumberland Utility set 84 LF of 48-in RCP between MH-12 and MH-13. Joint test scheduled Tuesday. Flange gaskets still pending from Mid-South Supply — needs PM push.
- John Hutchison: Equalization tank wall pour postponed to Tuesday due to heavy AM rain. Work shifted to bioretention basin CMU and rebar mat. One near-miss reported; RFI-014 still pending with civil engineer.
- Marcus Tran: Half weather day, equalization tank wall pour postponed to Tuesday. Bioretention basin CMU progressing. RFI-014 day 4 with civil engineer; PCO-007 pricing due Friday.
Daily reports
- Wes Carver· Owner's Representative0:58
Owner's rep on-site walk 14:00–15:30 with PM. Two items flagged: PCO-007 pricing commitment by Friday close; RFI-014 escalation from owner side tomorrow. Equalization tank forms observed clean. SWPPP holding.
Open report → - Sara Patel· Project Manager0:54
Site visit with Metro Water rep — pour prep on track for Tuesday. PCO-007 pricing commitment to owner reaffirmed for Friday. RFI-014 escalation tomorrow if no civil engineer response.
Open report → - Karen Boyd· Safety Officer1:02
Zero recordables. One near-miss (rebar bundle swing) — retrained on spot. Toolbox talk: rigging safety, 21 attendees. PPE issue: Premier saw operator gloves at EOL.
Open report → - Donny Steele· Ironworker Foreman0:42
Volunteer Rebar crew (4) tied ~70% of equalization tank G-J mat. Short on #5 rebar. Blower pad column ties still missing.
Open report → - Tom Briggs· Heavy Equipment Operator0:46
Cat 336 ran 3 hrs at pump station before rain shutdown. Skytrak 10054 idle 4 days — flagged for rental return. West gate muddy — recommend east-gate routing tomorrow.
Open report → - Luis Mendez· QC Officer0:39
Equalization tank wall forms within tolerance (Spec 03 30 00 §3.07). One punch item: anchor bolt B-1 at blower pad out of plumb. Metro Water rebar inspection rescheduled to Tuesday.
Open report → - Ricky Diaz· Concrete Foreman1:08
Pour prep on equalization tank E-7 paused for rain; forms preserved under canopy. Premier shifted to bioretention basin CMU (course 4 done, course 5 started). Tomorrow: pour 28 CY at 08:00 pending rebar inspection.
Open report → - Andre Hutch· Mechanical Foreman0:51
Cumberland Utility set 84 LF of 48-in RCP between MH-12 and MH-13. Joint test scheduled Tuesday. Flange gaskets still pending from Mid-South Supply — needs PM push.
Open report → - John Hutchison· Site Superintendent1:27
Equalization tank wall pour postponed to Tuesday due to heavy AM rain. Work shifted to bioretention basin CMU and rebar mat. One near-miss reported; RFI-014 still pending with civil engineer.
Open report → - Marcus Tran· Project Engineer1:13
Half weather day, equalization tank wall pour postponed to Tuesday. Bioretention basin CMU progressing. RFI-014 day 4 with civil engineer; PCO-007 pricing due Friday.
Open report →