Andre Hutch
Mechanical Foreman · Mon May 18, 2026 — Day 18 · voice note 0:51
What Andre said
Andre, Cumberland Utility, Monday. Three guys on site today. We set 84 linear feet of the 48-inch RCP between manhole 12 and 13, station fourteen-twenty to fifteen-oh-four. Joints all bedded, no leaks visually. Joint test scheduled for tomorrow with QC. Flange gaskets for the blower header still aren't here, Mid-South Supply says Friday — I told Sara last week, somebody needs to push them. We worked through the light rain in the trench, ground stayed workable. No issues, no injuries.
DR-2026-05-18-hutch
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
Cumberland Utility set 84 LF of 48-in RCP between MH-12 and MH-13. Joint test scheduled Tuesday. Flange gaskets still pending from Mid-South Supply — needs PM push.
- Storm drainage — 84 LF of 48-in RCP between MH-12 (sta 14+20) and MH-13 (sta 15+04). Joints bedded, no visible leaks.
- Cumberland Utility Services — 3 + foreman A. Hutch
- Short — flange gaskets for blower header (Mid-South Supply ETA Fri). Repeat issue — needs PM expedite push.
- Zero incidents
- Joint test MH-12 → MH-13 with QC
- Begin pipe set MH-13 → MH-14
Not mentioned today: equipment, weather, inspections.