Ironworker Foreman · Mon May 18, 2026 — Day 18 · voice note 0:42
Step 1 — the voice note
What Donny said
Donny. Steele. Monday. Four guys. Rained on us. Tied mat G to J in equalization tank, about 70 percent, ran out of #5 bars before quitting. Tomorrow we finish that and start the uppers if we get the bars. Almost lost a guy this morning, swing on the rebar bundle, rigger fixed it. No injuries. Need somebody to check on the column ties for the blower pad, still ain't here.
Step 2 — the generated daily report
DR-2026-05-18-steele
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
TL;DR
Volunteer Rebar crew (4) tied ~70% of equalization tank G-J mat. Short on #5 rebar. Blower pad column ties still missing.
Work completed
- Equalization tank — G-J bottom mat tied ~70% (Volunteer Rebar crew of 4)
Manpower
- Volunteer Rebar — 4 + foreman D. Steele
Materials
- Short — ran out of #5 bars before EOD. Need delivery for Tue.
- Short — column ties for blower pad, repeat issue (3+ days). Need expedite.
Safety
- Near-miss AM — rodbuster nearly struck by rebar bundle swing. Rigger retrained on the spot.
Open items
- Need #5 rebar for Tue AM
- Need PM to chase blower-pad column ties
Tomorrow's plan
- Finish G-J bottom mat
- Start H-J uppers if bars arrive
Not mentioned today: weather notes, equipment, inspections, delays detail.