Donny Steele

Ironworker Foreman · Mon May 18, 2026 — Day 18 · voice note 0:42

Step 1 — the voice note

What Donny said

Donny. Steele. Monday. Four guys. Rained on us. Tied mat G to J in equalization tank, about 70 percent, ran out of #5 bars before quitting. Tomorrow we finish that and start the uppers if we get the bars. Almost lost a guy this morning, swing on the rebar bundle, rigger fixed it. No injuries. Need somebody to check on the column ties for the blower pad, still ain't here.

Step 2 — the generated daily report

DR-2026-05-18-steele

Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.

TL;DR

Volunteer Rebar crew (4) tied ~70% of equalization tank G-J mat. Short on #5 rebar. Blower pad column ties still missing.

Work completed
  • Equalization tank — G-J bottom mat tied ~70% (Volunteer Rebar crew of 4)
Manpower
  • Volunteer Rebar — 4 + foreman D. Steele
Materials
  • Short — ran out of #5 bars before EOD. Need delivery for Tue.
  • Short — column ties for blower pad, repeat issue (3+ days). Need expedite.
Safety
  • Near-miss AM — rodbuster nearly struck by rebar bundle swing. Rigger retrained on the spot.
Open items
  • Need #5 rebar for Tue AM
  • Need PM to chase blower-pad column ties
Tomorrow's plan
  • Finish G-J bottom mat
  • Start H-J uppers if bars arrive

Not mentioned today: weather notes, equipment, inspections, delays detail.