Sara Patel

Project Manager · Mon May 18, 2026 — Day 18 · voice note 0:54

Step 1 — the voice note

What Sara said

Sara, Monday afternoon update. Was on site 14 to 15:30 with Wes from Metro Water. Walked the equalization tank pour prep before the rain came back, looks good for tomorrow. Wes asked about the valve vault again, PCO-007, I told him pricing by Friday. He's holding us to that. Confirmed with John we lost the morning to weather, he says recoverable. Anchor bolt RFI is still with the civil engineer — I'll call them tomorrow if no response by noon. Submittal 33-4100 in the same queue, that's the blower anchor pattern. Owner's monthly progress meeting is next Tuesday the 26th, we'll need a Friday rollup. That's it from me.

Step 2 — the generated daily report

DR-2026-05-18-patel

Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.

TL;DR

Site visit with Metro Water rep — pour prep on track for Tuesday. PCO-007 pricing commitment to owner reaffirmed for Friday. RFI-014 escalation tomorrow if no civil engineer response.

Schedule impact
  • Lost AM to weather. Per super, recoverable within float.
Open items
  • PCO-007 — pricing due to Metro Water by Fri 5/22 (owner reaffirmed)
  • RFI-014 — anchor bolt qty, day 4 open. Will call civil engineer tomorrow if no response by noon.
  • Submittal 33-4100 — same queue, pending civil engineer
Visitors
  • W. Carver (Nashville and Davidson County Metro Government) — site walk 14:00–15:30 with PM
Tomorrow's plan
  • Call civil engineer re: RFI-014 if no response by 12:00
  • Finalize PCO-007 pricing

Not mentioned today: manpower, work completed, materials, safety, inspections.