Marcus Tran

Project Engineer · Mon May 18, 2026 — Day 18 · voice note 1:13

Step 1 — the voice note

What Marcus said

Marcus, Monday May 18th, daily for the Ewing Creek. Day 18 of 240. Weather, AM was bad — heavy rain 10:20 to about 13:30, we logged it as a half weather day. Headcount today, 19 total. Walker self-perform four, Premier nine, Volunteer Rebar four, Cumberland Utility Services three, plus Karen and Luis floating. Work-wise, the big news is we postponed the equalization tank E-7 wall pour to tomorrow morning, IMI Concrete confirmed 28 yards at 8 AM. Premier shifted to bioretention basin CMU, completed course four north elevation and started course five. Volunteer Rebar tied roughly 70 percent of the G-J mat, they'll finish tomorrow. Hutch set 84 LF of 48-in RCP MH-12 to 13. Open items — RFI-014, anchor bolts, day four with the civil engineer, I emailed them again at 16:00. PCO-007 is due to Metro Water by Friday, I'm working pricing tonight. Submittal 33-4100 still pending. No safety incidents — Karen logged a near-miss this morning, no recordable. Tomorrow plan is the pour, plus Hutch joint testing, plus Volunteer Rebar upper mat. Twelve photos uploaded.

Step 2 — the generated daily report

DR-2026-05-18-tran

Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.

TL;DR

Half weather day, equalization tank wall pour postponed to Tuesday. Bioretention basin CMU progressing. RFI-014 day 4 with civil engineer; PCO-007 pricing due Friday.

Work completed
  • Bioretention basin N elev — CMU course 4 complete, course 5 started
  • Equalization tank — G-J rebar mat ~70% tied (Steele)
  • Storm drainage — 84 LF 48-in RCP MH-12 → MH-13 set
Manpower
  • Walker self-perform — 4 (incl. super, PE, 2 laborers)
  • Cumberland Concrete — 9 (R. Diaz)
  • Volunteer Rebar — 4 (D. Steele)
  • Cumberland Utility Services — 3 (A. Hutch)
  • Walker float — Karen (HSE), Luis (QC)
  • Total: 19 on site
Delays / disruptions
  • AM rain 10:20–13:30 — logged as half weather day. Equalization tank E-7 wall pour rescheduled to Tue 08:00.
Safety
  • Near-miss documented (see K. Boyd report). No recordable incidents.
Schedule impact
  • Critical path (equalization tank wall pour) slipped 1 day. Float remaining: 4 days. Recoverable.
Open items
  • RFI-014 — anchor bolt qty, day 4 open. Emailed civil engineer again 16:00.
  • PCO-007 — added valve vault pricing due to Metro Water by Fri 5/22.
  • Submittal 33-4100 — blower anchor pattern, pending civil engineer.
Tomorrow's plan
  • Pour equalization tank E-7 wall, 28 CY IMI Concrete, 08:00
  • Volunteer Rebar finish G-J mat, start H-J uppers
  • Hutch joint test MH-12 → MH-13
Photos
  • 12 photos uploaded, geotagged

Not mentioned today: materials/deliveries detail, equipment, inspections.