What Wes said

Wes Carver, Metro Water. Monday afternoon walk with Sara Patel, fourteen to fifteen-thirty. Two things I want on record. One, the valve vault at sta 18+00 — I expect pricing by Friday close, per Sara's commitment. That's PCO-007. Two, the anchor bolt RFI on the pump station — Walker's been waiting four days on the civil engineer, which is unacceptable for a critical-path item. I'm going to escalate from my side tomorrow. Also noted — equalization tank wall forms looked clean before the rain came back. SWPPP silt fence at the west entrance is holding up post-repair. That's it.

Step 2 — the generated daily report

DR-2026-05-18-carver

Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.

TL;DR

Owner's rep on-site walk 14:00–15:30 with PM. Two items flagged: PCO-007 pricing commitment by Friday close; RFI-014 escalation from owner side tomorrow. Equalization tank forms observed clean. SWPPP holding.

Inspections
  • Owner observation: equalization tank wall forms clean pre-rain
  • SWPPP silt fence west entrance — holding post-repair
Open items
  • PCO-007 — owner expects pricing by Fri 5/22 close
  • RFI-014 — owner to escalate from Metro Water side tomorrow
Visitors
  • W. Carver (Nashville and Davidson County Metro Government) — site walk 14:00–15:30 with S. Patel

Not mentioned today: manpower (owner rep, not on Walker crew), work completed (owner does not perform work), tomorrow plan.