Donny Steele
Ironworker Foreman · Tue May 19, 2026 — Day 19 · voice note 0:38
Step 1 — the voice note
What Donny said
Donny. Tuesday. Six today. Finished the G-J mat, started uppers, got about a third done. Bars came in this morning, eighteen tons of number five and six. Column ties still ain't here for the blower pad. Almost full crew tomorrow, seven, we should finish uppers.
Step 2 — the generated daily report
DR-2026-05-19-steele
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
TL;DR
Volunteer Rebar finished equalization tank G-J bottom mat, started uppers (~1/3 done). 18 tons #5/#6 rebar received. Blower-pad column ties STILL missing.
Work completed
- Equalization tank G-J bottom mat — completed
- Equalization tank G-J upper mat — ~33% tied
Manpower
- Volunteer Rebar — 6 + foreman D. Steele
Materials
- Received — 18 tons #5/#6 rebar (Volunteer Rebar PO)
- Short — column ties for blower pad (5+ days, ongoing)
Safety
- No incidents
Open items
- Blower-pad column ties — escalate to PM, 5+ day issue
Tomorrow's plan
- Crew up to 7
- Finish G-J upper mat
Not mentioned today: equipment, weather, inspections detail.