Sara Patel
Project Manager · Wed May 20, 2026 — Day 20 · voice note 0:51
What Sara said
Sara, Wednesday. RFI-014 closed today, big relief. PCO-007 pricing — I walked through it with Marcus, no surprises, 87,400 plus tax, line-item breakdown attached, sending to Wes Friday AM. Submittal R1 going Friday too. Gasket sub form Rinker comparable, ready to go to civil engineer tomorrow with Andre's data sheet. Thursday owner walk 09:00, I'll meet John at 08:30 for a pre-walk. Asked Marcus to draft the Friday weekly rollup tomorrow so we can review Friday morning before sending. That's it.
DR-2026-05-20-patel
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
RFI-014 closed. PCO-007 pricing locked ($87,400 + tax), sends Fri AM to Metro Water. Gasket sub to civil engineer Thu. Owner walk Thu 09:00.
- PCO-007 — pricing locked ($87,400 + tax), sends Fri AM
- Submittal 33-4100-R1 — sends Fri
- Gasket sub form — Rinker comparable, to civil engineer Thu AM
- 08:30 pre-walk w/ J. Hutchison
- 09:00 owner walk w/ W. Carver
- Submit gasket sub to civil engineer
- Marcus drafts Friday weekly rollup
Not mentioned today: work completed, manpower, safety, materials, weather.