Andre Hutch
Mechanical Foreman · Wed May 20, 2026 — Day 20 · voice note 0:53
What Andre said
Andre, Wednesday. Four guys, full crew. Set 65 feet of 48-inch RCP between MH-13 and 14, about 60 percent of the segment. Joints bedded, no leaks. Should finish the segment Friday, test Monday. Rinker gasket data sheet sent to Sara, she's pushing the sub form to the civil engineer tomorrow. Once the civil engineer signs we can install the blower header mid-next week. No injuries.
DR-2026-05-20-hutch
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
Hutch set 65 LF of 110 LF MH-13 → MH-14 segment (~60% complete). Rinker gasket data sheet sent to PM — sub form to civil engineer Thursday.
- Storm drainage MH-13 → MH-14 — 65 LF of 110 LF set (60%)
- Cumberland Utility Services — 4 + A. Hutch
- Zero incidents
- Gasket sub form (Rinker comparable) — to civil engineer Thu via PM
- Continue pipe set MH-13 → MH-14, target completion Fri
Not mentioned today: materials (no deliveries), weather, equipment, inspections.