Luis Mendez
QC Officer · Wed May 20, 2026 — Day 20 · voice note 0:56
What Luis said
Luis, Wednesday. E-7 wall strip inspected first thing, clean, no honeycomb, signed off per Spec 03 30 00 §3.07. Slab B-3 pour observation — three trucks, slump 4.0 all, on spec. RFI-014 closure verified — corrected anchor pattern from civil engineer is compliant with Spec 11-2150. Punch B-1 will be re-set Thursday by Steele's punch crew, I'll re-inspect Friday AM. ITP for bioretention basin CMU course 6 reviewed with Premier, ready for tomorrow.
DR-2026-05-20-mendez
Auto-generated from the transcript above. Per the Walker Dispatch construction daily-report format.
E-7 wall strip clean (Spec 03 30 00 §3.07). Slab B-3 pour on spec. RFI-014 close-out verified. Punch B-1 anchor re-set Thursday, re-inspect Friday AM.
- Equalization tank E-7 wall strip — clean, no honeycomb, compliant Spec 03 30 00 §3.07
- Slab B-3 pour QC — all 3 trucks slump 4.0, on spec
- RFI-014 closure — civil engineer pattern compliant Spec 11-2150
- ITP review bioretention basin CMU course 6 (Premier) — ready
- Punch B-1 anchor bolt — re-set Thu (Volunteer Rebar punch crew), re-inspect Fri AM
- Observe bioretention basin CMU course 6 pour
- Slab B-3 strip QC
- Volunteer Rebar pump station rebar layout review
Not mentioned today: manpower (QC float), safety, weather, materials.